United States › Grid › Interconnection queues › Iowa
SOLAR · MISOSolar project J4086, Wapello County
Solar project J4086, Wapello County is a 120 MW solar request in interconnection study in the MISO interconnection queue, in Wapello County, Iowa, connecting to ITC MIDWEST.
Queue statusIn planning
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4086
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Ottumwa Generation - Tri-County 161kV
- Location
- Wapello County, Iowa
- Technology
- Solar: 120 MW
- Total requested
- 120 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 7 October 2025
- Proposed online date
- June 2029
Location
Marker shows the centre of Wapello County; the queue data does not give exact sites.
Other requests in Wapello County
- Onshore wind project J3713, Wapello CountyOnshore wind · 200 MW · in study
- Battery storage project J4173, Wapello CountyBattery storage · 199 MW · in study
- Battery storage project J4172, Wapello CountyBattery storage · 99.0 MW · in study
- Coal project G718, Wapello CountyCoal · 900 MW · withdrawn
- Other project G129, Wapello CountyOther · 600 MW · withdrawn
- Coal project G719, Wapello CountyCoal · 600 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem