United States › Grid › Interconnection queues › Iowa
ONSHORE WIND · MISOOnshore wind project J3713, Wapello County
Onshore wind project J3713, Wapello County is a 200 MW onshore wind request in interconnection study in the MISO interconnection queue, in Wapello County, Iowa, connecting to ITC MIDWEST.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3713
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Ottumwa Generation - Woody 161kV
- Location
- Wapello County, Iowa
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 18 April 2024
- Proposed online date
- April 2028
Location
Marker shows the centre of Wapello County; the queue data does not give exact sites.
Other requests in Wapello County
- Battery storage project J4173, Wapello CountyBattery storage · 199 MW · in study
- Solar project J4086, Wapello CountySolar · 120 MW · in study
- Battery storage project J4172, Wapello CountyBattery storage · 99.0 MW · in study
- Coal project G718, Wapello CountyCoal · 900 MW · withdrawn
- Other project G129, Wapello CountyOther · 600 MW · withdrawn
- Coal project G719, Wapello CountyCoal · 600 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem