United States › Grid › Interconnection queues › Wyoming
GAS · WESTGas project 40969, Laramie County
Gas project 40969, Laramie County is a 115 MW gas request in interconnection study in the West interconnection queue, in Laramie County, Wyoming, connecting to Black Hills Cheyenne Light Fuel and Power Transmission.
- PlanningQueued Aug 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 40969
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Black Hills Cheyenne Light Fuel and Power Transmission
- Developer
- Cheyenne Light, Fuel and Power Company
- Connection point (POI)
- CPGS substation
- Location
- Laramie County, Wyoming
- Technology
- Gas: 115 MW
- Total requested
- 115 MW
- Service type
- Network resource (NRIS)
- Study phase
- Cluster Study
- Queue status
- Active
- Entered queue
- 11 August 2025
- Proposed online date
- January 2028
Location
Marker shows the centre of Laramie County; the queue data does not give exact sites.
Other requests in Laramie County
- Solar + storage project CLPT G21, Laramie CountySolar + storage · 400 MW · agreement signed
- Onshore wind project GI-TC-2024-16, Laramie CountyOnshore wind · 400 MW · agreement signed
- Solar + storage project CLPT G20, Laramie CountySolar + storage · 365 MW · agreement signed
- Other project CLPT G17, Laramie CountyOther · 300 MW · agreement signed
- Onshore wind project GI-TC-2024-15, Laramie CountyOnshore wind · 250 MW · agreement signed
- Onshore wind project CLPT G24, Laramie CountyOnshore wind · 200 MW · agreement signed
- Onshore wind project CLPT G23, Laramie CountyOnshore wind · 150 MW · agreement signed
- Gas project CLPT G22, Laramie CountyGas · 115 MW · agreement signed
- Gas project 37316, Laramie CountyGas · 600 MW · in study
- Onshore wind project 21-08242, Laramie CountyOnshore wind · 350 MW · in study
- Wind + storage project GI-CS-2025-04, Laramie CountyWind + storage · 330 MW · in study
- Wind + storage project 39873, Laramie CountyWind + storage · 198 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem