United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESQueue requests in study in Texas — page 22
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Elm Flats Solar SLF Solar + storage · Orca Falls Solar, LLC |
126 MW | In study |
| Zodiac Storage Battery storage · Grenergy USA |
126 MW | In study |
| Becerra Creek Storage 1 Battery storage · Bordas Renewable Energy, LLC |
126 MW | In study |
| Spinner Energy Storage Battery storage · GCI Wolf Energy Storage, LLC |
126 MW | In study |
| Becerra Creek Storage 2 Battery storage · Bordas Renewable Energy, LLC |
126 MW | In study |
| Momentum Hazy Jane BESS Battery storage · MOMENTUM HAZY JANE, LLC |
126 MW | In study |
| Three Ranches Solar Solar + storage · Three Ranches Energy LLC |
126 MW | In study |
| DMF Sagerton Solar SLF Solar + storage · Double Mountain Fork LLC |
126 MW | In study |
| Momentum Stout BESS Battery storage · Momentum STOUT, LLC |
126 MW | In study |
| Momentum Bock Battery storage · Momentum Bock, LLC |
125 MW | In study |
| Jumping Cactus Storage Battery storage · Dove Run Solar Project, LLC |
125 MW | In study |
| Saluga Ranch Storage Battery storage · Saluga Ranch Energy, LLC |
125 MW | In study |
| Houston County BESS Battery storage · Houston ESS, LLC |
125 MW | In study |
| TE Smith Storage 2 Battery storage · Smith II Battery Storage, LLC |
125 MW | In study |
| Journey Solar Solar · Journey Solar, LLC |
125 MW | In study |
| EMPower Odessa (TEF - Due Diligence) Gas · EMPOWER USA, LLC |
123 MW | In study |
| Sleepy Hollow BESS Battery storage · Sleepy Hollow BESS, LLC |
123 MW | In study |
| Great Hambino BESS Battery storage · Atascosa BESS, LLC |
123 MW | In study |
| Signal Hill BESS I Battery storage · Signal Hill Generating LLC |
123 MW | In study |
| Prairie Blossom Storage Battery storage · Prairie Blossom Storage, LLC |
123 MW | In study |
| Arnold Hills Storage Battery storage · Arnold Hills Storage, LLC |
123 MW | In study |
| Dove Wing Storage Battery storage · Dove Run Solar Project, LLC |
122 MW | In study |
| Sayle Solar SLF Solar + storage · Sayle Solar LLC |
122 MW | In study |
| Morning Glory Solar Solar · Armadillo Solar, LLC |
122 MW | In study |
| Sayle Storage SLF Solar + storage · Sayle Storage LLC |
122 MW | In study |
| BRP Ampato BESS Battery storage · BRP Ampato BESS LLC |
122 MW | In study |
| Bronc Rodeo Solar Project Solar · Energiekontor US Texas SP 16 LLC |
122 MW | In study |
| Nymphaea Solar Solar + storage · Nymphaea Solar, LLC |
121 MW | In study |
| Marengo BESS Battery storage · BRP BLUE TOPAZ 8, LLC |
121 MW | In study |
| Iron Cowboy Solar Solar + storage · Vaquero II Solar, LLC |
121 MW | In study |
| Wagyu BESS SLF Battery storage · Wagyu BESS, LLC |
121 MW | In study |
| Borden Dino Solar Solar + storage · Borden Dino Solar, LLC |
121 MW | In study |
| Neal Battery Solar + storage · CH Neal Battery LLC |
121 MW | In study |
| Rolling Plains BESS Battery storage · Haskell County BESS LLC |
120 MW | In study |
| Rosharon BESS Battery storage · Rosharon BESS LLC |
120 MW | In study |
| Riverwalk BESS Battery storage · RWE Solar Developement, LLC |
120 MW | In study |
| Kalina Solar Solar · Aurora Solar LLC |
120 MW | In study |
| Razorbill Storage Solar + storage · RWE Solar Development, LLC |
120 MW | In study |
| Solterra_canceled Solar Solar |
120 MW | Paused / redesign |
| Solar project GEN-2024-123, Shelby County Solar |
120 MW | In study |
| Buckaroo BESS Battery storage · Weatherford BESS LLC |
120 MW | In study |
| Wild Horse Desert Solar Solar + storage · Wild Horse Desert Solar, LLC |
120 MW | In study |
| Pradera Solar Solar + storage · Pradera Solar, LLC |
118 MW | In study |
| Roxton Solar Solar + storage · Roxton Solar, LLC |
117 MW | In study |
| Pioneer Hutt Solar Solar |
116 MW | Paused / redesign |
| Butcherbird Solar Solar · Butcherbird Solar, LLC |
116 MW | In study |
| Pioneer Hutt Solar (Alternative POI) Solar · NextEra Energy Interconnection Holdings LLC |
116 MW | In study |
| Marcos BESS Solar + storage · GRS BESS Texas Eight LLC |
116 MW | In study |
| Amphion Solar Phase 3 Solar · Amphion Solar, LLC |
115 MW | In study |
| Velado Storage SLF Solar + storage · Velado Solar, LLC |
115 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)1,398 · 327.9 GW
- SPP (Southwest Power Pool)61 · 16.6 GW
- MISO (Midcontinent)22 · 6,012 MW
- West (non-ISO utilities)5 · 997 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)