🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Three Ranches Solar

Three Ranches Solar is a 126 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Brewster County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0271
Grid region
ERCOT (Texas)
Developer
Three Ranches Energy LLC
Connection point (POI)
TAP 138kV #6680 Alamitto Creek - #60444 Hayter Ranch
Location
Brewster County, Texas
Technology
Solar: 126 MW · Battery
Total requested
126 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
14 February 2025
Proposed online date
January 2027

Location

Marker shows the centre of Brewster County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brewster County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem