Requests shown1,836452.0 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,836 requests ยท page 21 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2288, Ralls County
Solar
175 MWIn study Ralls, MOMISO Jan 2025target 2025
Solar + storage project T2-055, Juab County
Solar + storage
175 MWIn study Juab, UTWest Sep 2025target 2029
Eligius BESS
Battery storage ยท Eligius Storage LLC
175 MWIn study Hidalgo, TXERCOT Feb 2025target 2028
Nuclear project AH1-714, Lasalle County
Nuclear ยท Constellation Energy Generation, LLC
174 MWIn study Lasalle, ILPJM Apr 2025
Gas project IA-PNM-2025-20, Bernalillo County
Gas
172 MWIn study Bernalillo, NMWest Mar 2025target 2029
Solar + storage project J4170, Richland County
Solar + storage
172 MWIn study Richland, NDMISO Oct 2025target 2029
SR Dry Branch
Solar
172 MWIn study Twiggs, GASoutheast Jan 2025target 2029
Mount Storm Repower
Onshore wind ยท Renew Development Holdco LLC
171 MWIn study Barbour, WVPJM Jan 2025target 2025
Onshore wind project J3926, Webster County
Onshore wind
170 MWIn study Webster, IAMISO Mar 2025target 2030
Battery storage project ERAS-2025-029, Wyandotte County
Battery storage
170 MWIn study Wyandotte, KSSPP Oct 2025target 2027
Onshore wind project J3967, Huron County
Onshore wind
170 MWIn study Huron, MIMISO Apr 2025target 2029
Replacing 160 MW of Solar with 80 MW of Solar and 90 MW of BESS; Bell Solar
Solar + storage
170 MWIn study Shiawassee, MIMISO May 2025
Solar project 25-IC-1361, Cherokee County
Solar
170 MWIn study Cherokee, ALSoutheast Apr 2025target 2029
Solar + storage project GEN-2024-161, Jackson County
Solar + storage
170 MWIn study Jackson, OKSPP Mar 2025target 2030
Battery storage project S1127, Washington County
Battery storage
170 MWIn study Washington, MSMISO Nov 2025target 2027
Battery storage project GEN-2025-SR31, Madison County
Battery storage
170 MWIn study Madison, NESPP Nov 2025target 2026
Solar project J4069, Marathon County
Solar
170 MWIn study Marathon, WIMISO Oct 2025target 2030
Surplus; J291
Solar
169 MWIn study Scott, ILMISO Aug 2025target 2028
Bell Song Solar 2
Solar ยท Bell Song Solar, LLC 2
168 MWIn study Jim Hogg, TXERCOT Jun 2025target 2030
Bell Song Solar 3
Solar ยท Bell Song Solar, LLC_3
168 MWIn study Jim Hogg, TXERCOT Jun 2025target 2030
Bell Song Solar
Solar ยท Bell Song Solar, LLC
168 MWIn study Jim Hogg, TXERCOT Jun 2025target 2029
Solar project GEN-2024-297, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar project GEN-2024-296, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Gas project 758, Elmore County
Gas
167 MWIn study Elmore, IDWest Mar 2025target 2028
Solar project GEN-2024-298, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Wind + storage project J3962, Bay County
Wind + storage
165 MWIn study Bay, MIMISO Mar 2025target 2030
Solar project 25-IC-1355, Jasper County
Solar
165 MWIn study Jasper, MSSoutheast Apr 2025target 2029
Solar + storage project GI-CS-2025-12, Las Animas County
Solar + storage
165 MWIn study Las Animas, COWest Sep 2025target 2029
Solar + storage project 25-IC-1339, Hancock County
Solar + storage
165 MWIn study Hancock, GASoutheast Apr 2025target 2029
Onshore wind project E0036, Freeborn County
Onshore wind ยท Wisconsin Power and Light Company (WPL)
162 MWIn study Freeborn, MNMISO Aug 2025target 2028
Other project Q612, Coconino County
Other
161 MWIn study Coconino, AZWest May 2025target 2028
Solar project J2757, Cherokee County
Solar
160 MWIn study Cherokee, IAMISO Oct 2025target 2026
Solgen Solar
Solar + storage ยท Lampasas Hybrid Energy
160 MWIn study Lampasas, TXERCOT Apr 2025target 2029
Battery storage project T2-080, Salt Lake County
Battery storage
160 MWIn study Salt Lake, UTWest Sep 2025target 2027
Battery storage project GEN-2024-324, Chaves County
Battery storage
160 MWIn study Chaves, NMSPP Mar 2025target 2028
Solar + storage project 25-IC-1370, Perry County
Solar + storage
160 MWIn study Perry, ALSoutheast Apr 2025target 2028
Solar project J4047, Tuscola County
Solar
160 MWIn study Tuscola, MIMISO Aug 2025target 2028
Solar + storage project GEN-2024-219, Murray County
Solar + storage
160 MWIn study Murray, OKSPP Mar 2025target 2030
Solar + storage project GEN-2024-360, Seminole County
Solar + storage
160 MWIn study Seminole, OKSPP Mar 2025target 2029
Solar + storage project GEN-2024-122, Marion County
Solar + storage
160 MWIn study Marion, TXSPP Mar 2025target 2029
Solar + storage project T2-026, Albany County
Solar + storage
160 MWIn study Albany, WYWest Sep 2025target 2026
Gas project ERAS-2025-014, Lea County
Gas
160 MWIn study Lea, NMSPP Oct 2025target 2029
Gas project AH1-722, Union County
Gas ยท Parkway Generation Operating LLC
158 MWIn study Union, NJPJM Apr 2025
Solar + storage project AH1-543, Livingston County
Solar + storage ยท Golden Harvest Energy, LLC
157 MWIn study Livingston, ILPJM Feb 2025target 2025
Firefly Fields Storage
Solar + storage ยท Firefly Fields Energy Center LLC
157 MWIn study Colorado, TXERCOT Mar 2025target 2028
Solar project J3137, Pocahontas County
Solar
156 MWIn study Pocahontas, IAMISO Oct 2025target 2026
Gas project 25-00415, Clark County
Gas
156 MWIn study Clark, NVWest Jul 2025target 2028
Chimney Rock BESS
Battery storage ยท Taylor ESS, LLC
156 MWIn study Taylor, TXERCOT Feb 2025target 2028
Ranger BESS
Battery storage ยท Nova Clean Energy LLC
155 MWIn study Medina, TXERCOT Jun 2025target 2028
Battery storage project Q2503, Maricopa County
Battery storage
155 MWIn study Maricopa, AZWest Feb 2025target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)