🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Georgia

SOLAR · SOUTHEAST

SR Dry Branch

SR Dry Branch is a 172 MW solar request in interconnection study in the Southeast interconnection queue, in Twiggs County, Georgia, connecting to Georgia Transmission.

Queue statusIn planning
  1. PlanningQueued Jan 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-208
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Bonaire Primary - South Macon 230 kV Line
Location
Twiggs County, Georgia
Technology
Solar: 172 MW
Total requested
172 MW
Study phase
System Impact Study
Queue status
Active
Entered queue
9 January 2025
Proposed online date
December 2029

Location

Marker shows the centre of Twiggs County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Twiggs County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem