GAS · PJMGas project AH1-722, Union County
Gas project AH1-722, Union County is a 158 MW gas request in interconnection study in the PJM interconnection queue, in Union County, New Jersey, connecting to PSEG.
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH1-722
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PSEG
- Developer
- Parkway Generation Operating LLC
- Connection point (POI)
- Linden 230kV
- Location
- Union County, New Jersey
- Technology
- Gas: 158 MW
- Total requested
- 158 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 8 April 2025
Location
Marker shows the centre of Union County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Union County
- Gas project AH1-715, Union CountyGas · 149 MW · in study
- Linden 1, 2 & 3Gas · 750 MW · built
- Linden 1, 2 & 3Gas · 436 MW · built
- Tosco #6Gas · 180 MW · built
- Linden 5 & 6Gas · 120 MW · built
- Linden Generating StationGas · 61.0 MW · built
- Linden Generating StationGas · 47.0 MW · built
- Linden 1 & 2Gas · 44.0 MW · built
- Linden Generating StationGas · 36.0 MW · built
- Linden Generating StationGas · 23.0 MW · built
- Tosco #6Gas · 20.0 MW · built
- EF Kenilworth LLCGas · 17.9 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem