🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 191

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 191 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project G413, Mclean County
Onshore wind
150 MWWithdrawn / abandoned Mclean, ILMISO Mar 2004target 2006
Solar project J2792, Concordia Parish County
Solar
150 MWWithdrawn / abandoned Concordia Parish, LAMISO Aug 2022target 2026
Onshore wind project CS25-16, Adams County
Onshore wind
150 MWWithdrawn / abandoned Adams, WAWest Apr 2025target 2030
Onshore wind project G154, Deuel County
Onshore wind
150 MWWithdrawn / abandoned Deuel, SDMISO Nov 2001target 2003
Battery storage project AG2-306, Prince William County
Battery storage
150 MWWithdrawn / abandoned Prince William, VAPJM Mar 2021target 2023
Battery storage project J1446, Wright County
Battery storage
150 MWWithdrawn / abandoned Wright, MNMISO Apr 2019target 2022
Solar + storage project J2279, Ionia County
Solar + storage
150 MWWithdrawn / abandoned Ionia, MIMISO Jul 2021target 2025
Battery storage project 136, King County
Battery storage
150 MWWithdrawn / abandoned King, WAWest Oct 2022target 2025
Solar project J1414, Clay County
Solar
150 MWWithdrawn / abandoned Clay, ARMISO Apr 2019target 2022
Onshore wind project H019, Watonwan County
Onshore wind
150 MWWithdrawn / abandoned Watonwan, MNMISO Apr 2008target 2010
Onshore wind project J738, Green County
Onshore wind
150 MWWithdrawn / abandoned Green, WIMISO Nov 2016target 2020
Onshore wind project J2040, Dickinson County
Onshore wind
150 MWWithdrawn / abandoned Dickinson, IAMISO Aug 2021target 2024
North Chelsea (Fieldstone Power Station)
Battery storage · Fieldstone Power Station LLC
150 MWWithdrawn / abandoned Dutchess, NYNYISO Sep 2024
Onshore wind project G48, Benton County
Onshore wind · Washington Winds, Inc.
150 MWWithdrawn / abandoned Benton, WAWest Apr 2001target 2002
Beech Hollow
Gas
150 MWWithdrawn / abandoned Washington, PAPJM Jul 2004target 2015
Solar project 573, Henderson County
Solar
150 MWWithdrawn / abandoned Henderson, TNSoutheast Jun 2023target 2026
Solar project J2671, Arenac County
Solar
150 MWWithdrawn / abandoned Arenac, MIMISO Sep 2022target 2025
Battery storage project 231, Williamsburg County
Battery storage
150 MWWithdrawn / abandoned Williamsburg, SCSoutheast Jun 2023target 2028
Battery storage project AG2-113, Prince William County
Battery storage
150 MWWithdrawn / abandoned Prince William, VAPJM Jan 2021target 2022
Other project U1-086, Schuylkill County
Other
150 MWWithdrawn / abandoned Schuylkill, PAPJM Apr 2008target 2010
Onshore wind project J1400, Crittenden County
Onshore wind
150 MWWithdrawn / abandoned Crittenden, ARMISO Apr 2019target 2021
Solar project J1088, Shiawassee County
Solar
150 MWWithdrawn / abandoned Shiawassee, MIMISO Mar 2018target 2021
Solar project 669, Rhea County
Solar
150 MWWithdrawn / abandoned Rhea, TNSoutheast Oct 2024
Battery storage project GEN-2022-049, Franklin County
Battery storage
150 MWWithdrawn / abandoned Franklin, ARSPP Jun 20222025
Clear Water Solar
Solar · Hilliard Energy
150 MWWithdrawn / abandoned ERCOT Nov 2014target 2016
Onshore wind project 173, Sweetwater County
Onshore wind · Third Planet Windpower, LLC
150 MWWithdrawn / abandoned Sweetwater, WYWest Nov 2007target 2012
Solar project J698, Chicot County
Solar
150 MWWithdrawn / abandoned Chicot, ARMISO Jun 2017target 2015
Solar project 179866, Williamsburg County
Solar · Masked
150 MWWithdrawn / abandoned Williamsburg, SCSoutheast Jun 2021
Solar project AD2-181, Currituck County
Solar
150 MWWithdrawn / abandoned Currituck, NCPJM Mar 2018target 2018
Onshore wind project J085, Hillsdale County
Onshore wind
150 MWWithdrawn / abandoned Hillsdale, MIMISO Oct 2009target 2012
Solar project J4008, Henry County
Solar
150 MWWithdrawn / abandoned Henry, INMISO May 2025target 2027
Nolan Solar
Solar · Tenaska Solar XVII, LLC
150 MWWithdrawn / abandoned Nolan, TXERCOT Jan 2020target 2023
Onshore wind project GEN-2006-033, Geary County
Onshore wind
150 MWWithdrawn / abandoned Geary, KSSPP Aug 2006target 2008
Solar + storage project Q25, Kern County
Solar + storage
150 MWWithdrawn / abandoned Kern, CAWest Mar 2012target 2016
Battery storage project J3618, Clay County
Battery storage
150 MWWithdrawn / abandoned Clay, ARMISO Apr 2024target 2028
Onshore wind project 97, Judith Basin County
Onshore wind
150 MWWithdrawn / abandoned Judith Basin, MTWest Aug 2008target 2010
Solar project J990, Dubuque County
Solar
150 MWWithdrawn / abandoned Dubuque, IAMISO Mar 2018target 2020
Solar project 347, Lawrence County
Solar
150 MWWithdrawn / abandoned Lawrence, ALSoutheast Apr 2018
Battery storage project J3432, Lawrence County
Battery storage
150 MWWithdrawn / abandoned Lawrence, ILMISO Apr 2024target 2028
Solar + storage project IA-PNM-2021-20, Mckinley County
Solar + storage
150 MWWithdrawn / abandoned Mckinley, NMWest Jul 2021target 2024
Krenzer
Solar · ACE DevCo NC, LLC
150 MWWithdrawn / abandoned Monroe, NYNYISO Sep 2024
Solar project GI-2017-10, Arapahoe County
Solar
150 MWWithdrawn / abandoned Arapahoe, COWest Feb 2017target 2019
Onshore wind project G0737, Washington County
Onshore wind
150 MWWithdrawn / abandoned Washington, ORWest Apr 2022target 2026
Solar project GEN-2019-043, Fallon County
Solar
150 MWWithdrawn / abandoned Fallon, MTSPP May 20192023
Solar project 355, Lawrence County
Solar
150 MWWithdrawn / abandoned Lawrence, ALSoutheast Aug 2018
Solar project 354, Colbert County
Solar
150 MWWithdrawn / abandoned Colbert, ALSoutheast May 2019
Onshore wind project J931, Ottawa County
Onshore wind
150 MWWithdrawn / abandoned Ottawa, MIMISO Jun 2017target 2021
Battery Storage
Battery storage
150 MWWithdrawn / abandoned Essex, MAISO-NE Mar 2019target 2023
Battery storage project GEN-2024-203, Chaves County
Battery storage
150 MWWithdrawn / abandoned Chaves, NMSPP Mar 2025target 2030
Onshore wind project J452, Sanilac County
Onshore wind
150 MWWithdrawn / abandoned Sanilac, MIMISO May 2015
Page 191 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)