United States βΊ Grid βΊ Interconnection queues βΊ Montana
SOLAR Β· SPPSolar project GEN-2019-043, Fallon County
Solar project GEN-2019-043, Fallon County is a 150 MW solar request withdrawn in the SPP interconnection queue, in Fallon County, Montana, connecting to WAPA.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2019 (completed)
- Withdrawn / abandonedDec 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2023 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2019-043
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Baker-Mile City 230kV line
- Location
- Fallon County, Montana
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 23 May 2019
- Proposed online date
- December 2023
- Came online
- December 2023
- Withdrawn
- December 2022
Location
Marker shows the centre of Fallon County; the queue data does not give exact sites.
Other requests in Fallon County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem