ONSHORE WIND · MISOOnshore wind project G767, Fallon County
Onshore wind project G767, Fallon County is a 30.0 MW onshore wind request built and operating in the MISO interconnection queue, in Fallon County, Montana.
Request details
- Queue ID
- G767
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- existing 57 kV line
- Location
- Fallon County, Montana
- Technology
- Wind: 30.0 MW
- Total requested
- 30.0 MW
- Study phase
- DPP - SIS
- Queue status
- Operational
- Entered queue
- 20 March 2007
- Agreement signed
- 21 December 2007
- Proposed online date
- December 2009
- Came online
- December 2009
Location
Marker shows the centre of Fallon County; the queue data does not give exact sites.
Other requests in Fallon County