Battery storage project 136, King County

Battery storage project 136, King County is a 150 MW battery storage request withdrawn in the West interconnection queue, in King County, Washington, connecting to Puget Sound Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
136
Grid region
West (non-ISO utilities)
Utility / transmission owner
Puget Sound Energy
Connection point (POI)
Lat = 47.321872, Long = -122.0073
Location
King County, Washington
Technology
Battery: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
24 October 2022
Proposed online date
December 2025

Location

Marker shows the centre of King County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in King County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem