Hydro project 31 (PSE Merchant)

Hydro project 31 (PSE Merchant) is a 8.3 MW hydro request built and operating in the West interconnection queue, connecting to Puget Sound Energy.

Queue statusOperating
  1. PlanningQueued Feb 2011 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Mar 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
31 (PSE Merchant)
Grid region
West (non-ISO utilities)
Utility / transmission owner
Puget Sound Energy
Connection point (POI)
Snoqualmie Switching Station
Technology
Hydro: 8.3 MW
Total requested
8.3 MW
Service type
Network resource (NRIS)
Study phase
LGIA/ In Service
Queue status
Operational
Entered queue
14 February 2011
Proposed online date
March 2013

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in Β· Transmission lines in

Other requests in County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem