United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Southeast (non-ISO utilities) — page 16

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,067161.4 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,067 requests · page 16 of 22
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 376, Baker County
Solar · FPL
74.5 MWIn study Baker, FLSoutheast Nov 2019target 2027
Solar project 569, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2031
Solar project 20240829014, Barnwell County
Solar
74.5 MWIn study Barnwell, SCSoutheast target 2028
Solar project 312, Alachua County
Solar · Florida Renewable Partners, LLC
74.5 MWPaused / redesign Alachua, FLSoutheast Apr 2022target 2026
Solar project 537, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 101, Hillsborough County
Solar
74.5 MWIn study Hillsborough, FLSoutheast Apr 2023target 2025
Solar project 510, Manatee County
Solar · FPL
74.5 MWIn study Manatee, FLSoutheast Jan 2023target 2030
Solar project 428, Manatee County
Solar · FPL
74.5 MWIn study Manatee, FLSoutheast Mar 2022target 2026
Solar project 311, Alachua County
Solar · Florida Renewable Partners, LLC
74.5 MWPaused / redesign Alachua, FLSoutheast May 2022target 2025
Solar project 427, Indian River County
Solar · FPL
74.5 MWIn study Indian River, FLSoutheast Mar 2022target 2027
Harmony 2
Solar
74.5 MWIn study Osceola, FLSoutheast Dec 2020target 2024
Solar project 122, Hillsborough County
Solar
74.5 MWIn study Hillsborough, FLSoutheast May 2025target 2027
Solar project 404, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2026
Solar project 568, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2031
Solar project 565, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2032
Solar project 474, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2032
Solar project 284, Alachua County
Solar · Florida Renewable Partners, LLC
74.5 MWIn study Alachua, FLSoutheast Apr 2020target 2022
Solar project PP00001, Darlington County
Solar
74.2 MWUnder construction Darlington, SCSoutheast Sep 2024target 2028
Solar + storage project 333, Shelby County
Solar + storage
74.0 MWAgreement signed Shelby, TNSoutheast Oct 2017target 2024
Solar project 124, Aiken County
Solar
74.0 MWUnder construction Aiken, SCSoutheast Feb 2019target 2025
Solar project 955167, Johnston County
Solar
73.0 MWUnder construction Johnston, NCSoutheast Jun 2022target 2026
Solar project 572280, Greenwood County
Solar
72.0 MWAgreement signed Greenwood, SCSoutheast Jun 2022target 2028
Solar project 650, Muhlenberg County
Solar
72.0 MWIn study Muhlenberg, KYSoutheast Sep 2024target 2029
Solar project 25-IC-1357, Monroe County
Solar
71.0 MWIn study Monroe, ALSoutheast Apr 2025target 2029
Solar project 569164, Newberry County
Solar
70.7 MWIn study Newberry, SCSoutheast Jun 2022target 2027
Altamaha Green Energy
Other
70.0 MWIn study Wayne, GASoutheast Aug 2024target 2028
Solar project 962965, Lenoir County
Solar
70.0 MWIn study Lenoir, NCSoutheast Oct 2024
Solar project 963472, Robeson County
Solar
70.0 MWIn study Robeson, NCSoutheast Sep 2024
Solar project 193, Levy County
Solar · Origis Development LLC
70.0 MWIn study Levy, FLSoutheast Aug 2017target 2021
Solar project 920651, Darlington County
Solar
70.0 MWIn study Darlington, SCSoutheast Sep 2023
Other project PP00036, Robeson County
Other
70.0 MWIn study Robeson, NCSoutheast Jul 2025target 2028
Other project PP00045, Lenoir County
Other
70.0 MWIn study Lenoir, NCSoutheast Aug 2025target 2029
Solar project 48968, Chester County
Solar
69.8 MWAgreement signed Chester, SCSoutheast Nov 2017target 2027
Solar project 388, Simpson County
Solar
69.0 MWAgreement signed Simpson, KYSoutheast Aug 2019target 2025
Solar project IC-1176, Glascock County
Solar
68.5 MWPaused / redesign Glascock, GASoutheast Sep 2023target 2028
Solar project 25RSC-003, Mcminn County
Solar
68.0 MWIn study Mcminn, TNSoutheast Jul 2025target 2031
Solar project 515, Haywood County
Solar
67.0 MWAgreement signed Haywood, TNSoutheast Aug 2022target 2025
Solar project 299, Lake County
Solar
67.0 MWAgreement signed Lake, TNSoutheast Jul 2016target 2020
Solar project 920659, Wayne County
Solar
67.0 MWAgreement signed Wayne, NCSoutheast Sep 2023
Solar project 522, Choctaw County
Solar
67.0 MWIn study Choctaw, MSSoutheast Sep 2022target 2026
Other project PP00037, Wayne County
Other
67.0 MWIn study Wayne, NCSoutheast Jul 2025target 2029
Gas project 20211118004, Aiken County
Gas · DESC - Generation
65.9 MWIn study Aiken, SCSoutheast target 2024
Gas project 20211118005, Berkeley County
Gas · DESC - Generation
65.4 MWIn study Berkeley, SCSoutheast target 2026
Solar project 915787, Florence County
Solar
65.0 MWIn study Florence, SCSoutheast Sep 2023
Nuclear project 25-IC-1302, Appling County
Nuclear
65.0 MWIn study Appling, GASoutheast Mar 2025target 2031
Solar project 915773, Dillon County
Solar
65.0 MWIn study Dillon, SCSoutheast Sep 2023
Other project PP00050, Cumberland County
Other
65.0 MWIn study Cumberland, NCSoutheast Sep 2025target 2029
SR Millen
Solar
65.0 MWIn study Jenkins, GASoutheast Jan 2025target 2029
Solar project 963044, Cumberland County
Solar · Duke Energy Progress LLC
65.0 MWIn study Cumberland, NCSoutheast Sep 2024
Gas project 20211118003, Aiken County
Gas · DESC - Generation
64.9 MWIn study Aiken, SCSoutheast target 2024
Page 16 of 22

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)