🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Solar project 101, Hillsborough County

Solar project 101, Hillsborough County is a 74.5 MW solar request in interconnection study in the Southeast interconnection queue, in Hillsborough County, Florida, connecting to Tampa Electric Company.

Queue statusIn planning
  1. PlanningQueued Apr 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
101
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tampa Electric Company
Connection point (POI)
Little Manatee River Substation, Hillsborough County, Florida
Location
Hillsborough County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
Transitional Cluster Study Complete
Queue status
Active
Entered queue
24 April 2023
Proposed online date
December 2025

Location

Marker shows the centre of Hillsborough County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Hillsborough County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem