Solar project 106, Hillsborough County

Solar project 106, Hillsborough County is a 74.5 MW solar request built and operating in the Southeast interconnection queue, in Hillsborough County, Florida, connecting to Tampa Electric Company.

Queue statusOperating
  1. PlanningQueued Jun 2023 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
106
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tampa Electric Company
Connection point (POI)
Mines Substation, Hillsborough County, Florida
Location
Hillsborough County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
Transitional Cluster Study Complete
Queue status
Operational
Entered queue
15 June 2023
Proposed online date
December 2025

Location

Marker shows the centre of Hillsborough County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Hillsborough County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem