Gas project 62, Hillsborough County

Gas project 62, Hillsborough County is a 186 MW gas request built and operating in the Southeast interconnection queue, in Hillsborough County, Florida, connecting to Tampa Electric Company.

Queue statusOperating
  1. PlanningQueued Aug 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Sep 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
62
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tampa Electric Company
Connection point (POI)
Gannon Substation, Hillsborough County, Florida
Location
Hillsborough County, Florida
Technology
Gas: 186 MW
Total requested
186 MW
Service type
Network resource (NRIS)
Study phase
Interconnection Agreement Executed
Queue status
Operational
Entered queue
14 August 2019
Proposed online date
September 2023

Location

Marker shows the centre of Hillsborough County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Hillsborough County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem