United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Solar project 112, Hillsborough County

Solar project 112, Hillsborough County is a 74.5 MW solar request in interconnection study in the Southeast interconnection queue, in Hillsborough County, Florida, connecting to Tampa Electric Company.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
112
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tampa Electric Company
Connection point (POI)
Sun City Substation, Hillsborough County, Florida
Location
Hillsborough County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Energy only (ERIS)
Study phase
Transitional Cluster Study Complete
Queue status
Active
Entered queue
31 March 2024
Proposed online date
December 2026

Location

Marker shows the centre of Hillsborough County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Hillsborough County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem