SOLAR · SOUTHEAST

Solar project IC-1176, Glascock County

Solar project IC-1176, Glascock County is a 68.5 MW solar request suspended in the Southeast interconnection queue, in Glascock County, Georgia, connecting to Southern Company.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IC-1176
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Branch - Springhill Church 230 kV Line
Location
Glascock County, Georgia
Technology
Solar: 68.5 MW
Total requested
68.5 MW
Service type
Energy only (ERIS)
Queue status
Suspended
Entered queue
26 September 2023
Proposed online date
January 2028

Location

Marker shows the centre of Glascock County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia