Solar project 312, Alachua County

Solar project 312, Alachua County is a 74.5 MW solar request suspended in the Southeast interconnection queue, in Alachua County, Florida, connecting to Duke Energy Florida.

Queue statusPaused / redesign
  1. PlanningQueued Apr 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
312
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Florida Renewable Partners, LLC
Connection point (POI)
Bronson - Newberry
Location
Alachua County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
NRIS and ERIS
Queue status
Suspended
Entered queue
22 April 2022
Proposed online date
June 2026

Location

Marker shows the centre of Alachua County; the queue data does not give exact sites.