Interconnection queue in MISO (Midcontinent) — page 14

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,646350.1 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,646 requests · page 14 of 33
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J2572, Hamilton County
Battery storage
200 MWIn study Hamilton, INMISO Sep 2022target 2025
Battery storage project J2607, Montgomery County
Battery storage
200 MWIn study Montgomery, ILMISO Sep 2022target 2026
Solar project J1562, Mississippi County
Solar
200 MWAgreement signed Mississippi, ARMISO Jun 2020target 2025
Onshore wind project J2509, Tippecanoe County
Onshore wind
200 MWIn study Tippecanoe, INMISO Sep 2022target 2025
Onshore wind project J4120, Lenawee County
Onshore wind
200 MWIn study Lenawee, MIMISO Sep 2025target 2030
Onshore wind project J1270, Palo Alto County
Onshore wind
200 MWIn study Palo Alto, IAMISO Apr 2019target 2024
Solar project J1431, St. James Parish County
Solar
200 MWAgreement signed St. James Parish, LAMISO Apr 2019target 2024
Solar + storage project J1891, Attala County
Solar + storage
200 MWIn study Attala, MSMISO Aug 2021target 2027
Solar + storage project J2893, Holmes County
Solar + storage
200 MWIn study Holmes, MSMISO Sep 2022target 2027
Battery storage project J2601, Wabasha County
Battery storage
200 MWIn study Wabasha, MNMISO Sep 2022target 2026
Battery storage project J3251, Genesee County
Battery storage
200 MWIn study Genesee, MIMISO Apr 2024target 2028
Solar project J2667, Sanilac County
Solar
200 MWIn study Sanilac, MIMISO Sep 2022target 2025
Solar project J3095, Ford County
Solar
200 MWIn study Ford, ILMISO Sep 2022target 2025
Solar project J4092, Beauregard Parish County
Solar
200 MWIn study Beauregard Parish, LAMISO Oct 2025target 2030
Solar project J3287, Osceola County
Solar
200 MWIn study Osceola, MIMISO Apr 2024target 2028
Solar project J2848, Hamilton County
Solar
200 MWIn study Hamilton, INMISO Nov 2025target 2025
Solar project J1190, Clinton County
Solar
200 MWAgreement signed Clinton, IAMISO Jan 2019target 2025
Onshore wind project J2577, Cross County
Onshore wind
200 MWIn study Cross, ARMISO Sep 2022target 2025
Solar + storage project J2388, Macon County
Solar + storage
200 MWIn study Macon, ILMISO Sep 2022target 2026
Solar + storage project J3979, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Solar project J2676, Huron County
Solar
200 MWIn study Huron, MIMISO Sep 2022target 2025
Solar project J2228, Concordia Parish County
Solar
200 MWIn study Concordia Parish, LAMISO Dec 2021target 2027
Solar project J2486, Monroe County
Solar
200 MWIn study Monroe, MIMISO Sep 2022target 2025
Battery storage project J1898, Olmsted County
Battery storage
200 MWIn study Olmsted, MNMISO Aug 2021target 2024
Solar project J3847, Jefferson County
Solar
200 MWIn study Jefferson, ILMISO Jan 2025target 2029
Solar project J1849, Hardin County
Solar
200 MWIn study Hardin, TXMISO Nov 2021target 2028
Battery storage project J4002, Edgar County
Battery storage
200 MWIn study Edgar, ILMISO Apr 2025target 2030
Onshore wind project J3928, Bay County
Onshore wind
200 MWIn study Bay, MIMISO Jan 2025target 2030
Onshore wind project J2938, Knox County
Onshore wind
200 MWIn study Knox, ILMISO Sep 2022target 2025
Battery storage project J3780, Buchanan County
Battery storage
200 MWIn study Buchanan, IAMISO Apr 2024target 2028
Onshore wind project J3749, Lyon County
Onshore wind
200 MWIn study Lyon, MNMISO Apr 2024target 2028
Battery storage project J2998, St. Clair County
Battery storage
200 MWIn study St. Clair, ILMISO Sep 2022target 2025
Solar project J2181, Mississippi County
Solar
200 MWIn study Mississippi, ARMISO Jul 2022target 2027
Solar project J2298, Greene County
Solar
200 MWIn study Greene, ARMISO Nov 2021target 2028
Battery storage project J3440, Daviess County
Battery storage
200 MWIn study Daviess, MOMISO Apr 2024target 2028
Solar project J1684, Starke County
Solar
200 MWIn study Starke, INMISO Aug 2023target 2029
Onshore wind project J4129, Otter Tail County
Onshore wind
200 MWIn study Otter Tail, MNMISO Oct 2025target 2029
Solar project J3522, Cass County
Solar
200 MWIn study Cass, NDMISO Mar 2024target 2028
Solar project J1062, Washtenaw County
Solar
200 MWAgreement signed Washtenaw, MIMISO Mar 2018target 2023
Solar + storage project J3879, Jackson County
Solar + storage
200 MWIn study Jackson, INMISO May 2024target 2030
Battery storage project J3298, Tazewell County
Battery storage
200 MWIn study Tazewell, ILMISO Apr 2024target 2027
Battery storage project J4019, Calhoun County
Battery storage
200 MWIn study Calhoun, MIMISO May 2025target 2030
Solar project J1558, Pope County
Solar
200 MWIn study Pope, ARMISO Jun 2020target 2026
Battery storage project J1894, Kalamazoo County
Battery storage
200 MWIn study Kalamazoo, MIMISO Oct 2021target 2024
Solar project J3959, Grundy County
Solar
200 MWIn study Grundy, MOMISO Apr 2025target 2029
Surplus; J992
Battery storage
200 MWIn study Cass, INMISO Jun 2025target 2026
Solar + storage project J3058, Arkansas County
Solar + storage
200 MWIn study Arkansas, ARMISO Jul 2025target 2025
Onshore wind project J2930, Henderson County
Onshore wind
200 MWIn study Henderson, KYMISO Sep 2022target 2025
Solar project J1306, Perry County
Solar
200 MWAgreement signed Perry, ILMISO Apr 2019target 2024
Wind + storage project J3122, Crittenden County
Wind + storage
200 MWIn study Crittenden, ARMISO Sep 2022target 2025
Page 14 of 33

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)