United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project J3749, Lyon County

Onshore wind project J3749, Lyon County is a 200 MW onshore wind request in interconnection study in the MISO interconnection queue, in Lyon County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3749
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
LYON COUNTY
Location
Lyon County, Minnesota
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
11 April 2024
Proposed online date
June 2028

Location

Marker shows the centre of Lyon County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Lyon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem