United States › Grid › Interconnection queues › Minnesota
ONSHORE WIND · MISOOnshore wind project J3749, Lyon County
Onshore wind project J3749, Lyon County is a 200 MW onshore wind request in interconnection study in the MISO interconnection queue, in Lyon County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3749
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- LYON COUNTY
- Location
- Lyon County, Minnesota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 11 April 2024
- Proposed online date
- June 2028
Location
Marker shows the centre of Lyon County; the queue data does not give exact sites.
Other requests in Lyon County
- Other project G177, Lyon CountyOther · 5.0 MW · agreement signed
- Onshore wind project J3326, Lyon CountyOnshore wind · 250 MW · in study
- Battery storage project J3894, Lyon CountyBattery storage · 250 MW · in study
- Solar project J3021, Lyon CountySolar · 235 MW · in study
- Onshore wind project H081, Lyon CountyOnshore wind · 201 MW · built
- Solar project J400, Lyon CountySolar · 62.5 MW · built
- Onshore wind project GI-0606, Lyon CountyOnshore wind · 10.0 MW · built
- Onshore wind project GI-0601, Lyon CountyOnshore wind · 10.0 MW · built
- Gas project J131, Lyon CountyGas · 300 MW · withdrawn
- Onshore wind project G841, Lyon CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project J3346, Lyon CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project G842, Lyon CountyOnshore wind · 250 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem