United States › Grid › Interconnection queues › Minnesota
SOLAR · MISOSolar project J400, Lyon County
Solar project J400, Lyon County is a 62.5 MW solar request built and operating in the MISO interconnection queue, in Lyon County, Minnesota.
Request details
- Queue ID
- J400
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Lyon County 115kV Substation
- Location
- Lyon County, Minnesota
- Technology
- Solar: 62.5 MW
- Total requested
- 62.5 MW
- Study phase
- DPP - SIS
- Queue status
- Operational
- Entered queue
- 10 November 2014
- Agreement signed
- 18 October 2016
- Proposed online date
- June 2017
- Came online
- June 2017
Location
Marker shows the centre of Lyon County; the queue data does not give exact sites.
Other requests in Lyon County
- Other project G177, Lyon CountyOther · 5.0 MW · agreement signed
- Onshore wind project J3326, Lyon CountyOnshore wind · 250 MW · in study
- Battery storage project J3894, Lyon CountyBattery storage · 250 MW · in study
- Solar project J3021, Lyon CountySolar · 235 MW · in study
- Onshore wind project J3749, Lyon CountyOnshore wind · 200 MW · in study
- Onshore wind project H081, Lyon CountyOnshore wind · 201 MW · built
- Onshore wind project GI-0606, Lyon CountyOnshore wind · 10.0 MW · built
- Onshore wind project GI-0601, Lyon CountyOnshore wind · 10.0 MW · built
- Gas project J131, Lyon CountyGas · 300 MW · withdrawn
- Onshore wind project G841, Lyon CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project J3346, Lyon CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project G842, Lyon CountyOnshore wind · 250 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem