United States › Grid › Interconnection queues › Minnesota

SOLAR · MISO

Solar project J400, Lyon County

Solar project J400, Lyon County is a 62.5 MW solar request built and operating in the MISO interconnection queue, in Lyon County, Minnesota.

Queue statusOperating
  1. PlanningQueued Nov 2014 (completed)
  2. ConsentedOct 2016 (completed)
  3. Construction (completed)
  4. OperatingJun 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J400
Grid region
MISO (Midcontinent)
Connection point (POI)
Lyon County 115kV Substation
Location
Lyon County, Minnesota
Technology
Solar: 62.5 MW
Total requested
62.5 MW
Study phase
DPP - SIS
Queue status
Operational
Entered queue
10 November 2014
Agreement signed
18 October 2016
Proposed online date
June 2017
Came online
June 2017

Location

Marker shows the centre of Lyon County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Lyon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem