United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in the USA (2019 requests) β€” page 12

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown589109.2 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

589 requests Β· page 12 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Limestone Solar
Solar
20.0 MWAgreement signed Union, PAPJM Sep 2019target 2027
Jackson Center Solar II
Solar
20.0 MWAgreement signed Mercer, PAPJM Aug 2019target 2026
Charles County Solar II
Solar
20.0 MWPaused / redesign Charles, MDPJM Apr 2019target 2027
Jakes Hollow Solar
Solar
20.0 MWPaused / redesign Elk, PAPJM Sep 2019target 2027
Mansfield #3
Battery storage
20.0 MWAgreement signed Warren, NJPJM Sep 2019target 2025
Valley Solar
Solar Β· Valley Solar NY LLC
20.0 MWIn study Tioga, NYNYISO Apr 2019target 2027
GDC Saco Solar
Solar
20.0 MWAgreement signed York, MEISO-NE Oct 2019target 2027
Houses Corner Storage
Battery storage
20.0 MWAgreement signed Sussex, NJPJM Sep 2019target 2026
NY37 Solar
Solar Β· Sandy Creek Solar LLC
20.0 MWIn study Jefferson, NYNYISO May 2019target 2026
Solar project GI-2019-5, Garfield County
Solar
19.9 MWIn study Garfield, COWest Apr 2019target 2020
Walnut Solar I
Solar
19.9 MWAgreement signed King And Queen, VAPJM Apr 2019target 2026
Angelina Solar I
Solar
18.0 MWAgreement signed Preble, OHPJM Aug 2019target 2028
Welcome Solar III, LLC
Solar + storage
17.9 MWAgreement signed Crawford, PAPJM Apr 2019target 2026
Battery storage project 49220, Buncombe County
Battery storage Β· Duke Energy Progress, LLC
17.3 MWAgreement signed Buncombe, NCSoutheast Oct 2019target 2026
West Baldwin Solar
Solar
17.1 MWAgreement signed Cumberland, MEISO-NE Oct 2019target 2029
Other project J1247, St. Mary Parish County
Other
17.0 MWUnder construction St. Mary Parish, LAMISO Apr 20192023
G Morris Solar
Solar
17.0 MWPaused / redesign Dauphin, PAPJM Sep 2019target 2026
Concho Solar I
Solar
17.0 MWPaused / redesign Queen Anne's, MDPJM Feb 2019target 2024
BL-Diamond Bear Rocks
Solar
16.3 MWAgreement signed Adams, PAPJM Sep 2019target 2026
Ce-Filmore
Solar
16.0 MWPaused / redesign Centre, PAPJM Mar 2019target 2027
Shands Energy Center
Battery storage
15.7 MWAgreement signed Sussex, VAPJM Jan 2019target 2025
FU-Hanks Solar
Solar
15.7 MWPaused / redesign Fulton, PAPJM Sep 2019target 2026
Gas project GEN-2019-019, Woodbury County
Gas
15.2 MWAgreement signed Woodbury, IASPP Apr 20192022
Luyster Creek Energy Storage 3
Battery storage Β· Eastern Generation, LLC
15.0 MWIn study Queens, NYNYISO Oct 2019target 2027
Arthur Kill Energy Storage 1
Battery storage Β· Lighthouse Arthur Kill, LLC
15.0 MWIn study Richmond, NYNYISO Apr 2019
Jarratt Solar
Solar
14.9 MWAgreement signed Greensville, VAPJM Sep 2019target 2027
Solar project AF2-039, Clearfield County
Solar
13.5 MWAgreement signed Clearfield, PAPJM Nov 2019target 2026
CL-Route 58 B
Solar
13.5 MWPaused / redesign Clarion, PAPJM Sep 2019target 2026
Highbanks Solar
Solar Β· Highbanks Solar LLC
12.5 MWIn study Livingston, NYNYISO May 2019target 2026
SunEast Hooversville Solar
Solar
10.0 MWPaused / redesign Somerset, PAPJM Oct 2019target 2026
West Lorain 138 kV Power Plant
Gas
8.0 MWAgreement signed Lorain, OHPJM Oct 2019target 2028
Maryland Offshore Wind Energy Project (MOWEP)
Offshore wind
7.3 MWPaused / redesign Sussex, DEPJM Apr 2019target 2027
Solar
Solar
7.0 MWAgreement signed Kennebec, MEISO-NE Aug 2019target 2022
Solar project 85, Adams County
Solar
5.0 MWIn study Adams, WAWest Apr 2019target 2020
Solar + storage project 84, Stevens County
Solar + storage
5.0 MWIn study Stevens, WAWest Apr 2019target 2024
Hydro project 1186, Bannock County
Hydro Β· Commercial Energy Management, Inc.
0.9 MWAgreement signed Bannock, IDWest Oct 2019target 2021
Solar project TCS-40, Benton County
Solar Β· Oregon State University
0.8 MWAgreement signed Benton, ORWest Jul 2019target 2024
Solar project TCS-38, Benton County
Solar Β· Oregon State University
0.3 MWAgreement signed Benton, ORWest Jul 2019target 2024
Solar project TCS-39, Benton County
Solar Β· Oregon State University
0.2 MWAgreement signed Benton, ORWest Jul 2019target 2024
Page 12 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)