United States › Grid › Interconnection queues › Iowa
GAS · SPPGas project GEN-2019-019, Woodbury County
Gas project GEN-2019-019, Woodbury County is a 15.2 MW gas request with a signed interconnection agreement in the SPP interconnection queue, in Woodbury County, Iowa, connecting to NIPCO.
Queue statusConsented
- PlanningQueued Apr 2019 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingMar 2022 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2019-019
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NIPCO
- Connection point (POI)
- Siouxland 69kV
- Location
- Woodbury County, Iowa
- Technology
- Gas: 15.2 MW
- Total requested
- 15.2 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 24 April 2019
- Proposed online date
- March 2022
- Came online
- March 2022
Location
Marker shows the centre of Woodbury County; the queue data does not give exact sites.
Other requests in Woodbury County
- Coal project J279, Woodbury CountyCoal · 30.0 MW · built
- Solar + storage project J3088, Woodbury CountySolar + storage · 300 MW · withdrawn
- Coal project J358, Woodbury CountyCoal · 280 MW · withdrawn
- Gas project J359, Woodbury CountyGas · 232 MW · withdrawn
- Coal project J357, Woodbury CountyCoal · 135 MW · withdrawn
- Onshore wind project J2352, Woodbury CountyOnshore wind · 118 MW · withdrawn
- Onshore wind project J253, Woodbury CountyOnshore wind · 48.3 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem