United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Jarratt Solar

Jarratt Solar is a 14.9 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Greensville County, Virginia, connecting to Dominion.

Queue statusConsented
  1. PlanningQueued Sep 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF1-292
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Fields 34.5kV
Location
Greensville County, Virginia
Technology
Solar: 14.9 MW
Total requested
14.9 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Active
Entered queue
30 September 2019
Proposed online date
August 2027

Location

Marker shows the centre of Greensville County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Greensville County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem