SOLAR · PJM

Sadler Solar

Sadler Solar is a 100 MW solar request built and operating in the PJM interconnection queue, in Greensville County, Virginia, connecting to Dominion.

Queue statusOperating
  1. PlanningQueued Apr 2016 (completed)
  2. ConsentedJan 2019 (completed)
  3. Construction (completed)
  4. OperatingJan 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AB2-100
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Clubhouse-Lakeview 230kV
Location
Greensville County, Virginia
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
27 April 2016
Agreement signed
29 January 2019
Proposed online date
December 2021
Came online
January 2021

Location

Marker shows the centre of Greensville County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Greensville County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem