United States › Grid › Interconnection queues › North Carolina
BATTERY STORAGE · SOUTHEASTBattery storage project 49220, Buncombe County
Battery storage project 49220, Buncombe County is a 17.3 MW battery storage request with a signed interconnection agreement in the Southeast interconnection queue, in Buncombe County, North Carolina, connecting to Duke Energy Progress.
Queue statusConsented
- PlanningQueued Oct 2019 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 49220
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Progress
- Developer
- Duke Energy Progress, LLC
- Location
- Buncombe County, North Carolina
- Technology
- Battery: 17.3 MW
- Total requested
- 17.3 MW
- Study phase
- Engineering Design - In Progress
- Queue status
- Active
- Entered queue
- 8 October 2019
- Proposed online date
- March 2026
Location
Marker shows the centre of Buncombe County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Buncombe County
- Battery storage project 191894, Buncombe CountyBattery storage · 30.5 MW · under construction
- Solar project 24747, Buncombe CountySolar · 9.5 MW · agreement signed
- Gas project 900845, Buncombe CountyGas · 19.9 MW · in study
- Gas project 900843, Buncombe CountyGas · 19.9 MW · in study
- Gas project 957688, Buncombe CountyGas · 5.0 MW · in study
- Gas project PP00019, Buncombe CountyGas · 5.0 MW · in study
- Gas project 957691, Buncombe CountyGas · 5.0 MW · in study
- Gas project PP00020, Buncombe CountyGas · 5.0 MW · in study
- Gas project 8598, Buncombe CountyGas · 280 MW · built
- Gas project 8597, Buncombe CountyGas · 280 MW · built
- Gas project 8599, Buncombe CountyGas · 470 MW · withdrawn
- Gas project 8600, Buncombe CountyGas · 280 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem