Solar project 24747, Buncombe County

Solar project 24747, Buncombe County is a 9.5 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Buncombe County, North Carolina, connecting to Duke Energy Progress.

Queue statusConsented
  1. PlanningQueued Dec 2016 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24747
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Developer
Duke Energy Progress, LLC
Connection point (POI)
Asheville Energy Complex
Location
Buncombe County, North Carolina
Technology
Solar: 9.5 MW
Total requested
9.5 MW
Service type
Network resource (NRIS)
Study phase
Engineering Design - Pending
Queue status
Active
Entered queue
15 December 2016
Proposed online date
March 2026

Location

Marker shows the centre of Buncombe County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Buncombe County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem