GAS · SOUTHEASTGas project 8597, Buncombe County
Gas project 8597, Buncombe County is a 280 MW gas request built and operating in the Southeast interconnection queue, in Buncombe County, North Carolina, connecting to Duke Energy Progress.
Request details
- Queue ID
- 8597
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Progress
- Developer
- Duke Energy Progress, LLC
- Connection point (POI)
- Asheville Energy Complex 115 kV Switchyard; Asheville Plant
- Location
- Buncombe County, North Carolina
- Technology
- Gas: 280 MW
- Total requested
- 280 MW
- Study phase
- Commercial Operation - Commercial Operation Date Declared
- Queue status
- Operational
- Entered queue
- 15 December 2015
- Came online
- December 2019
Location
Marker shows the centre of Buncombe County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Buncombe County
- Battery storage project 191894, Buncombe CountyBattery storage · 30.5 MW · under construction
- Battery storage project 49220, Buncombe CountyBattery storage · 17.3 MW · agreement signed
- Solar project 24747, Buncombe CountySolar · 9.5 MW · agreement signed
- Gas project 900845, Buncombe CountyGas · 19.9 MW · in study
- Gas project 900843, Buncombe CountyGas · 19.9 MW · in study
- Gas project 957688, Buncombe CountyGas · 5.0 MW · in study
- Gas project PP00019, Buncombe CountyGas · 5.0 MW · in study
- Gas project 957691, Buncombe CountyGas · 5.0 MW · in study
- Gas project PP00020, Buncombe CountyGas · 5.0 MW · in study
- Gas project 8598, Buncombe CountyGas · 280 MW · built
- Gas project 8599, Buncombe CountyGas · 470 MW · withdrawn
- Gas project 8600, Buncombe CountyGas · 280 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem