United States › Grid › Interconnection queues › New Jersey

BATTERY STORAGE · PJM

Mansfield #3

Mansfield #3 is a 20.0 MW battery storage request with a signed interconnection agreement in the PJM interconnection queue, in Warren County, New Jersey, connecting to JCPL.

Queue statusConsented
  1. PlanningQueued Sep 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF1-328
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Hackettstown-Pohatcong 34.5 kV
Location
Warren County, New Jersey
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
30 September 2019
Proposed online date
October 2025

Location

Marker shows the centre of Warren County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Warren County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem