United States › Grid › Interconnection queues › New York

SOLAR · NYISO

Valley Solar

Valley Solar is a 20.0 MW solar request in interconnection study in the NYISO interconnection queue, in Tioga County, New York, connecting to NYSEG.

Queue statusIn planning
  1. PlanningQueued Apr 2019 (current stage)
  2. ConsentedJan 2021 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
828
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Valley Solar NY LLC
Connection point (POI)
Owego 34.5kV Substation
Location
Tioga County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
SIS, FS
Queue status
Active
Entered queue
24 April 2019
Agreement signed
22 January 2021
Proposed online date
January 2027

Location

Marker shows the centre of Tioga County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Tioga County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem