United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR Β· NYISOCDG Owego 2, LLC
CDG Owego 2, LLC is a 19.6 MW solar request withdrawn in the NYISO interconnection queue, in Tioga County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2020 (completed)
- Withdrawn / abandonedFeb 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1082
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- CDG Owego 2
- Connection point (POI)
- Line 513 - 34.5KV
- Location
- Tioga County, New York
- Technology
- Solar: 19.6 MW
- Total requested
- 19.6 MW
- Queue status
- Withdrawn
- Entered queue
- 27 August 2020
- Withdrawn
- February 2021
Location
Marker shows the centre of Tioga County; the queue data does not give exact sites.
Other requests in Tioga County
- Southern Tier Energy CenterBattery storage Β· 200 MW Β· in study
- Valley SolarSolar Β· 20.0 MW Β· in study
- Tioga County EnergyGas Β· 700 MW Β· withdrawn
- Southern Tier Energy CenterBattery storage Β· 200 MW Β· withdrawn
- Endless Mountain WindOnshore wind Β· 150 MW Β· withdrawn
- Dean WindOnshore wind Β· 150 MW Β· withdrawn
- Canfield WindOnshore wind Β· 120 MW Β· withdrawn
- Sidecar SolarSolar Β· 100 MW Β· withdrawn
- SidecarSolar Β· 50.0 MW Β· withdrawn
- Owego SolarSolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem