🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

ONSHORE WIND · NYISO

Endless Mountain Wind

Endless Mountain Wind is a 150 MW onshore wind request withdrawn in the NYISO interconnection queue, in Tioga County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2006 (completed)
  2. Withdrawn / abandonedJul 2006 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
218
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Gamesa Energy USA
Connection point (POI)
Homer City-Watercure 345kV
Location
Tioga County, New York
Technology
Wind: 150 MW
Total requested
150 MW
Queue status
Withdrawn
Entered queue
3 July 2006
Withdrawn
July 2006

Location

Marker shows the centre of Tioga County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Tioga County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem