United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Battery storage interconnection queue in the USA — page 12

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,226417.8 GW
Active in queue417.8 GW2,226 requests
Agreement signed76.1 GW459 requests
Withdrawn3,516554.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,226 requests · page 12 of 45
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project IC-1187, Wilkinson County
Battery storage
220 MWAgreement signed Wilkinson, GASoutheast Oct 2023target 2027
Battery storage project GEN-2025-SR8, Noble County
Battery storage
220 MWIn study Noble, OKSPP May 2025target 2027
Battery storage project J3646, St. Clair County
Battery storage
220 MWIn study St. Clair, MIMISO Apr 2024target 2028
Two Barbaras BESS
Battery storage · Two Barbaras BESS
217 MWAgreement signed Montgomery, TXERCOT Mar 2024target 2029
Pez Rojo BESS
Battery storage · Pez Rojo BESS, LLC
217 MWIn study Harris, TXERCOT Jul 2024target 2029
Dorian Storage
Battery storage
214 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2034
Zeus BESS
Battery storage
214 MWAgreement signed San Joaquin, CACAISO Apr 2021target 2031
Weston Storage
Battery storage
214 MWIn study San Bernardino, CACAISO Apr 2021target 2031
Sandhill Energy Storage
Battery storage · Xcel Energy
214 MWIn study Olmsted, MNMISO Aug 2025target 2025
Frigatebird Storage
Battery storage
214 MWIn study San Diego, CACAISO Apr 2021target 2035
Rock Rose BESS
Battery storage · Rock Rose Energy Storage LLC
212 MWAgreement signed Fort Bend, TXERCOT Sep 2023target 2026
Bessie Storage
Battery storage · Bessie Energy Storage, LLC
211 MWIn study Starr, TXERCOT Feb 2022target 2026
Cumulus Grid BESS
Battery storage · Cumulus Grid, LLC
211 MWAgreement signed Ellis, TXERCOT Mar 2022target 2028
Val Vista Grid BESS 2
Battery storage · Val Vista Grid, LLC
211 MWIn study Hidalgo, TXERCOT Oct 2021target 2028
Guadalupe Battery Storage Project
Battery storage · Guadalupe Power Partners, LP
211 MWIn study Guadalupe, TXERCOT Nov 2023target 2027
Freestone Battery Storage Project
Battery storage · Freestone Power Generation, LLC
211 MWIn study Freestone, TXERCOT Feb 2024target 2028
Battery storage project S0027, Walla Walla County
Battery storage
210 MWIn study Walla Walla, WAWest Feb 2024target 2026
Battery storage project AI1-185, Augusta County
Battery storage
210 MWIn study Augusta, VAPJM Sep 2022target 2027
Val Vista Grid BESS 1
Battery storage · Val Vista Grid, LLC
209 MWIn study Hidalgo, TXERCOT Aug 2020target 2028
Moonlit Bayou Storage
Battery storage · Moonlit Bayou Energy Center, LLC
209 MWIn study Fayette, TXERCOT Feb 2024target 2028
Battery storage project GEN-2025-SR30, Dewey County
Battery storage
209 MWIn study Dewey, OKSPP Aug 2025target 2027
Sorghum BESS
Battery storage · Blue Creek BESS, LLC
209 MWAgreement signed Wharton, TXERCOT Apr 2024target 2027
Starlit Pasture Storage
Battery storage · Starlit Pasture Energy Center, LLC
209 MWIn study Washington, TXERCOT Aug 2024target 2029
Revolution BESS
Battery storage · Nova Clean Energy LLC
209 MWIn study La Salle, TXERCOT May 2024target 2027
Battery storage project MPC04600, Eddy County
Battery storage
209 MWIn study Eddy, NDMISO Nov 2025target 2028
Alwest BESS
Battery storage · Castleman Power
209 MWIn study Anderson, TXERCOT Aug 2021target 2028
Jolly Rock Storage Center
Battery storage · Jolly Rock Storage Center LLC
209 MWIn study Young, TXERCOT Dec 2024target 2029
New Minglewood Energy Center
Battery storage · Nova Clean Energy LLC
208 MWIn study Ward, TXERCOT May 2024target 2027
Ferdinand Grid BESS II
Battery storage · Coval Infrastructure DevCo LLC
208 MWIn study Bexar, TXERCOT Dec 2024target 2027
Bypass Battery Storage
Battery storage · Bypass BESS LLC
208 MWAgreement signed Fort Bend, TXERCOT Aug 2021target 2025
Amite Energy Storage II
Battery storage · NextEra Energy Resources Development, LLC
208 MWIn study Tangipahoa Parish, LAMISO Aug 2025target 2028
Burnet Bay Storage
Battery storage · TOCE TX BESS 4, LLC
208 MWIn study Harris, TXERCOT Sep 2024target 2027
Anatole Renewable Energy Storage
Battery storage · Eustace Storage LLC
208 MWAgreement signed Henderson, TXERCOT Jun 2022target 2027
Cottonseed Energy Storage
Battery storage · Cottonseed Energy Storage LLC
208 MWIn study Wharton, TXERCOT Nov 2023target 2027
Woodland Energy Storage
Battery storage · Woodland Energy Storage, LLC
208 MWIn study Bosque, TXERCOT Dec 2023target 2030
Reforzar BESS 1
Battery storage · Tempus Power management LLC
208 MWIn study Brooks, TXERCOT Dec 2024target 2028
Reforzar Bess 2
Battery storage · Tempus Power management LLC
208 MWIn study Brooks, TXERCOT Dec 2024target 2028
Bravo BESS
Battery storage · Bravo BESS LLC
207 MWIn study Webb, TXERCOT Nov 2024target 2027
Liberty Senate Energy Storage 1
Battery storage · Senate Solar LLC
207 MWIn study Jack, TXERCOT Oct 2021target 2027
Old Roman Energy Center
Battery storage · Nova Clean Energy LLC
207 MWIn study Reagan, TXERCOT Oct 2024target 2027
Pintail Pass BESS
Battery storage · Pintail Pass BESS, LLC
207 MWAgreement signed San Patricio, TXERCOT Apr 2022target 2026
Vertus Energy Storage
Battery storage · VERTUS ENERGY STORAGE LLC
207 MWAgreement signed Galveston, TXERCOT Oct 2023target 2026
Metro BESS
Battery storage · Metro BESS LLC
207 MWIn study Caldwell, TXERCOT Feb 2025target 2030
Alamosa Storage
Battery storage
207 MWPaused / redesign Wilbarger, TXERCOT Oct 2021
Aldrin 138 BESS
Battery storage · Aldrin Energy Storage LLC
207 MWAgreement signed Brazoria, TXERCOT May 2023target 2027
Battery storage project GEN-2019-011, Yoakum County
Battery storage
207 MWAgreement signed Yoakum, TXSPP Apr 2019target 2028
BRP Hemera BESS
Battery storage · BRP Hemera BESS LLC
207 MWIn study Deaf Smith, TXERCOT Dec 2021target 2029
BRP Rhine BESS
Battery storage · BRP Rhine BESS LLC
207 MWIn study Ward, TXERCOT Aug 2020target 2028
BRP Volans BESS
Battery storage · BRP Volans BESS LLC
207 MWIn study Winkler, TXERCOT Aug 2020target 2027
BRP Pyxis BESS
Battery storage · BRP Pyxis BESS LLC
207 MWIn study Ward, TXERCOT Sep 2020target 2028
Page 12 of 45

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)