BATTERY STORAGE · ERCOT

Burnet Bay Storage

Burnet Bay Storage is a 208 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Harris County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0548
Grid region
ERCOT (Texas)
Developer
TOCE TX BESS 4, LLC
Connection point (POI)
tap 138kV 40390 Crosby - 40790 Haney
Location
Harris County, Texas
Technology
Battery: 208 MW
Total requested
208 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
10 September 2024
Proposed online date
June 2027

Location

Marker shows the centre of Harris County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Harris County