United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESProjects with signed interconnection agreements in the USA — page 12
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Windstar I Alternate Wind + storage |
240 MW | Agreement signed |
| Sycamore Cross Solar Solar |
240 MW | Agreement signed |
| Midway Peaking Gas |
240 MW | Agreement signed |
| Bracero Pecan Storage Battery storage · Bracero Pecan Storage LLC |
238 MW | Agreement signed |
| Onshore wind project GI-53, Nodaway County Onshore wind |
238 MW | Agreement signed |
| Onshore wind project GI-2004-2, Baca County Onshore wind |
238 MW | Agreement signed |
| Solar + storage project GI-DISIS-2022-04, Kit Carson County Solar + storage |
237 MW | Agreement signed |
| Gas project IA-PNM-2017-14, San Juan County Gas |
236 MW | Agreement signed |
| Photon Solar 1 2 SLF Solar · GulfStar Power, LLC |
236 MW | Agreement signed |
| Monte Cristo 1 Wind Onshore wind · Terra-Gen |
235 MW | Agreement signed |
| Sapphire Solar Solar + storage |
234 MW | Agreement signed |
| Monte Cristo II Wind Onshore wind · Monte Cristo Windpower II, LLC |
234 MW | Agreement signed |
| Sbranch Solar Solar · Bernard Creek Solar, LLC |
234 MW | Agreement signed |
| Taormina Storage Battery storage · Taormina Storage Project LLC |
232 MW | Agreement signed |
| Adelite Storage Battery storage · Adelite Storage Project LLC |
232 MW | Agreement signed |
| Lavender Storage Project Battery storage · Lavender Storage Project LLC |
232 MW | Agreement signed |
| Buffalo Gap 2 Wind Repower Onshore wind · Buffalo Gap Wind Farm 2, LLC |
232 MW | Agreement signed |
| Solar project GEN-2021-018, Noble County Solar |
231 MW | Agreement signed |
| Onshore wind project GEN-2018-125, Lancaster County Onshore wind |
231 MW | Agreement signed |
| Onshore wind project GI-61, Nodaway County Onshore wind |
230 MW | Agreement signed |
| Geothermal project Company LM, Lyon County Geothermal |
230 MW | Agreement signed |
| Heartland 2 Solar + storage |
228 MW | Agreement signed |
| Heartland 1 Solar + storage |
228 MW | Agreement signed |
| Pin Peaking Energy Center 1 (TEF- Due Diligence) Gas · PIN OAK CREEK ENERGY CENTER, LLC |
228 MW | Agreement signed |
| Pin Peaking Energy Center 2 (TEF- Due Diligence) Gas · PIN OAK CREEK ENERGY CENTER, LLC |
228 MW | Agreement signed |
| Diver Solar Solar · Diver Solar |
226 MW | Agreement signed |
| Rubicon Alpha Wind Onshore wind · Throckmorton Wind, LLC |
226 MW | Agreement signed |
| Solar project IC-1206, Laurens County Solar |
225 MW | Agreement signed |
| Solar project GEN-2021-049, Lancaster County Solar |
225 MW | Agreement signed |
| Solar + storage project GEN-2020-079, Cherokee County Solar + storage |
225 MW | Agreement signed |
| Baldy Mesa Solar + storage |
225 MW | Agreement signed |
| Solar project J1502, Juneau County Solar |
225 MW | Agreement signed |
| Allium Hybrid Solar + storage |
225 MW | Agreement signed |
| Castro Solar Solar · Castro Solar One, LLC |
225 MW | Agreement signed |
| Tolivar Power Plant (TEF- Due Diligence) Gas · Pecos Power Plant, LLC |
225 MW | Agreement signed |
| Oystercatcher Solar Solar · Oystercatcher Solar, LLC |
222 MW | Agreement signed |
| Gas project Company 230, Clark County Gas |
222 MW | Agreement signed |
| Gas project Company 231, Clark County Gas |
222 MW | Agreement signed |
| Solar project GEN-2018-131, Pierce County Solar |
221 MW | Agreement signed |
| Onshore wind project CS23-06, Whitman County Onshore wind |
221 MW | Agreement signed |
| Onshore wind project GEN-2015-066, Pawnee County Onshore wind |
220 MW | Agreement signed |
| Battery storage project Company 211, Clark County Battery storage |
220 MW | Agreement signed |
| Battery storage project IC-1187, Wilkinson County Battery storage |
220 MW | Agreement signed |
| Eastern Cottontail Solar Solar |
220 MW | Agreement signed |
| Crowded Star Solar Solar + storage · Jones City Solar, LLC |
219 MW | Agreement signed |
| Two Barbaras BESS Battery storage · Two Barbaras BESS |
217 MW | Agreement signed |
| Onshore wind project GEN-2017-233, Grady County Onshore wind |
215 MW | Agreement signed |
| Onshore wind project GEN-2018-082, Pittsburg County Onshore wind |
215 MW | Agreement signed |
| Dorian Storage Battery storage |
214 MW | Agreement signed |
| Zeus BESS Battery storage |
214 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)578 · 119.3 GW
- CAISO (California)235 · 96.2 GW
- West (non-ISO utilities)349 · 60.6 GW
- Southeast (non-ISO utilities)192 · 37.8 GW
- SPP (Southwest Power Pool)212 · 37.6 GW
- PJM (Mid-Atlantic, Midwest)343 · 35.0 GW
- MISO (Midcontinent)187 · 28.1 GW
- ISO-NE (New England)45 · 8,609 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)