United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA — page 12

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,141423.2 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,141 requests · page 12 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Windstar I Alternate
Wind + storage
240 MWAgreement signed Kern, CACAISO Apr 20062012
Sycamore Cross Solar
Solar
240 MWAgreement signed Isle Of Wight, VAPJM Mar 2017target 2026
Midway Peaking
Gas
240 MWAgreement signed Fresno, CACAISO Jan 20052009
Bracero Pecan Storage
Battery storage · Bracero Pecan Storage LLC
238 MWAgreement signed Reeves, TXERCOT Nov 2022target 2027
Onshore wind project GI-53, Nodaway County
Onshore wind
238 MWAgreement signed Nodaway, MOSoutheast May 2016target 2018
Onshore wind project GI-2004-2, Baca County
Onshore wind
238 MWAgreement signed Baca, COWest Feb 2004
Solar + storage project GI-DISIS-2022-04, Kit Carson County
Solar + storage
237 MWAgreement signed Kit Carson, COWest May 2022target 2027
Gas project IA-PNM-2017-14, San Juan County
Gas
236 MWAgreement signed San Juan, NMWest Oct 2017target 2022
Photon Solar 1 2 SLF
Solar · GulfStar Power, LLC
236 MWAgreement signed Wharton, TXERCOT Sep 2024target 2026
Monte Cristo 1 Wind
Onshore wind · Terra-Gen
235 MWAgreement signed Hidalgo, TXERCOT Apr 2017target 2025
Sapphire Solar
Solar + storage
234 MWAgreement signed Riverside, CACAISO Apr 2020target 2034
Monte Cristo II Wind
Onshore wind · Monte Cristo Windpower II, LLC
234 MWAgreement signed Hidalgo, TXERCOT Apr 2017target 2028
Sbranch Solar
Solar · Bernard Creek Solar, LLC
234 MWAgreement signed Wharton, TXERCOT Jan 2019target 2026
Taormina Storage
Battery storage · Taormina Storage Project LLC
232 MWAgreement signed Bexar, TXERCOT Apr 2022target 2029
Adelite Storage
Battery storage · Adelite Storage Project LLC
232 MWAgreement signed Milam, TXERCOT Jun 2022target 2027
Lavender Storage Project
Battery storage · Lavender Storage Project LLC
232 MWAgreement signed Bexar, TXERCOT Feb 2022target 2029
Buffalo Gap 2 Wind Repower
Onshore wind · Buffalo Gap Wind Farm 2, LLC
232 MWAgreement signed Nolan, TXERCOT Dec 2024target 2026
Solar project GEN-2021-018, Noble County
Solar
231 MWAgreement signed Noble, OKSPP Apr 2021target 2028
Onshore wind project GEN-2018-125, Lancaster County
Onshore wind
231 MWAgreement signed Lancaster, NESPP Nov 2018target 2031
Onshore wind project GI-61, Nodaway County
Onshore wind
230 MWAgreement signed Nodaway, MOSoutheast May 2017target 2019
Geothermal project Company LM, Lyon County
Geothermal
230 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Heartland 2
Solar + storage
228 MWAgreement signed Fresno, CACAISO May 2017target 2028
Heartland 1
Solar + storage
228 MWAgreement signed Fresno, CACAISO May 2017target 2028
Pin Peaking Energy Center 1 (TEF- Due Diligence)
Gas · PIN OAK CREEK ENERGY CENTER, LLC
228 MWAgreement signed Freestone, TXERCOT Apr 2023target 2026
Pin Peaking Energy Center 2 (TEF- Due Diligence)
Gas · PIN OAK CREEK ENERGY CENTER, LLC
228 MWAgreement signed Freestone, TXERCOT Apr 2023target 2026
Diver Solar
Solar · Diver Solar
226 MWAgreement signed Limestone, TXERCOT Sep 2022target 2026
Rubicon Alpha Wind
Onshore wind · Throckmorton Wind, LLC
226 MWAgreement signed Haskell, TXERCOT May 2022target 2027
Solar project IC-1206, Laurens County
Solar
225 MWAgreement signed Laurens, GASoutheast Nov 2023target 2028
Solar project GEN-2021-049, Lancaster County
Solar
225 MWAgreement signed Lancaster, NESPP Apr 2021target 2029
Solar + storage project GEN-2020-079, Cherokee County
Solar + storage
225 MWAgreement signed Cherokee, KSSPP Apr 2020target 2028
Baldy Mesa
Solar + storage
225 MWAgreement signed San Bernardino, CACAISO May 2017target 2026
Solar project J1502, Juneau County
Solar
225 MWAgreement signed Juneau, WIMISO Jun 2020target 2026
Allium Hybrid
Solar + storage
225 MWAgreement signed San Benito, CACAISO Apr 2021target 2030
Castro Solar
Solar · Castro Solar One, LLC
225 MWAgreement signed Castro, TXERCOT Feb 2018target 2028
Tolivar Power Plant (TEF- Due Diligence)
Gas · Pecos Power Plant, LLC
225 MWAgreement signed Reeves, TXERCOT Jul 2024target 2027
Oystercatcher Solar
Solar · Oystercatcher Solar, LLC
222 MWAgreement signed Ellis, TXERCOT May 2019target 2026
Gas project Company 230, Clark County
Gas
222 MWAgreement signed Clark, NVWest Sep 2022target 2024
Gas project Company 231, Clark County
Gas
222 MWAgreement signed Clark, NVWest Sep 2022target 2024
Solar project GEN-2018-131, Pierce County
Solar
221 MWAgreement signed Pierce, NESPP Nov 2018target 2031
Onshore wind project CS23-06, Whitman County
Onshore wind
221 MWAgreement signed Whitman, WAWest Apr 2023target 2028
Onshore wind project GEN-2015-066, Pawnee County
Onshore wind
220 MWAgreement signed Pawnee, OKSPP Oct 20152025
Battery storage project Company 211, Clark County
Battery storage
220 MWAgreement signed Clark, NVWest Jan 2022target 2029
Battery storage project IC-1187, Wilkinson County
Battery storage
220 MWAgreement signed Wilkinson, GASoutheast Oct 2023target 2027
Eastern Cottontail Solar
Solar
220 MWAgreement signed Fairfield, OHPJM Jan 2019target 2028
Crowded Star Solar
Solar + storage · Jones City Solar, LLC
219 MWAgreement signed Jones, TXERCOT Jan 2019target 2026
Two Barbaras BESS
Battery storage · Two Barbaras BESS
217 MWAgreement signed Montgomery, TXERCOT Mar 2024target 2029
Onshore wind project GEN-2017-233, Grady County
Onshore wind
215 MWAgreement signed Grady, OKSPP Nov 2017target 2027
Onshore wind project GEN-2018-082, Pittsburg County
Onshore wind
215 MWAgreement signed Pittsburg, OKSPP Nov 2018target 2030
Dorian Storage
Battery storage
214 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2034
Zeus BESS
Battery storage
214 MWAgreement signed San Joaquin, CACAISO Apr 2021target 2031
Page 12 of 43

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)