United States › Grid › Interconnection queues › Kansas
SOLAR + STORAGE · SPPSolar + storage project GEN-2020-079, Cherokee County
Solar + storage project GEN-2020-079, Cherokee County is a 225 MW solar + storage request with a signed interconnection agreement in the SPP interconnection queue, in Cherokee County, Kansas, connecting to EDE.
Queue statusConsented
- PlanningQueued Apr 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Aug 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2020-079
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- EDE
- Connection point (POI)
- Riverton-Neosho 161kV line
- Location
- Cherokee County, Kansas
- Technology
- Solar: 225 MW · Battery
- Total requested
- 225 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 30 April 2020
- Proposed online date
- August 2028
Location
Marker shows the centre of Cherokee County; the queue data does not give exact sites.
Other requests in Cherokee County
- Other project GEN-2024-GR4, Cherokee CountyOther · 27.1 MW · agreement signed
- Gas project GEN-2004-017, Cherokee CountyGas · 250 MW · built
- Gas project GEN-2014-028, Cherokee CountyGas · 50.0 MW · built
- Solar project GEN-2023-194, Cherokee CountySolar · 225 MW · withdrawn
- Solar + storage project GEN-2023-004, Cherokee CountySolar + storage · 200 MW · withdrawn
- Battery storage project GEN-2023-191, Cherokee CountyBattery storage · 74.0 MW · withdrawn
- Gas project GEN-2003-010, Cherokee CountyGas · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem