United States › Grid › Interconnection queues › Kansas
GAS · SPPGas project GEN-2014-028, Cherokee County
Gas project GEN-2014-028, Cherokee County is a 50.0 MW gas request built and operating in the SPP interconnection queue, in Cherokee County, Kansas, connecting to EDE.
Request details
- Queue ID
- GEN-2014-028
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- EDE
- Connection point (POI)
- Riverton 161kV
- Location
- Cherokee County, Kansas
- Technology
- Gas: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 25 September 2014
- Proposed online date
- April 2016
- Came online
- April 2016
Location
Marker shows the centre of Cherokee County; the queue data does not give exact sites.
Other requests in Cherokee County
- Solar + storage project GEN-2020-079, Cherokee CountySolar + storage · 225 MW · agreement signed
- Other project GEN-2024-GR4, Cherokee CountyOther · 27.1 MW · agreement signed
- Gas project GEN-2004-017, Cherokee CountyGas · 250 MW · built
- Solar project GEN-2023-194, Cherokee CountySolar · 225 MW · withdrawn
- Solar + storage project GEN-2023-004, Cherokee CountySolar + storage · 200 MW · withdrawn
- Battery storage project GEN-2023-191, Cherokee CountyBattery storage · 74.0 MW · withdrawn
- Gas project GEN-2003-010, Cherokee CountyGas · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem