πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2023-004, Cherokee County

Solar + storage project GEN-2023-004, Cherokee County is a 200 MW solar + storage request withdrawn in the SPP interconnection queue, in Cherokee County, Kansas, connecting to EDE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2023 (completed)
  2. Withdrawn / abandonedDec 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-004
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
EDE
Connection point (POI)
Baxter Springs 161 kV Substation
Location
Cherokee County, Kansas
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
26 July 2023
Proposed online date
December 2026
Withdrawn
December 2023

Location

Marker shows the centre of Cherokee County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Cherokee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem