United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2025 requests) — page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,836452.0 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,836 requests · page 11 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Vista Bluff Wind II "Alternate POI"
Onshore wind · Vista Bluff Windpower, LLC
290 MWIn study Upton, TXERCOT Sep 2025target 2029
Vista Bluff Wind I "Alternate POI"
Onshore wind · Vista Bluff Windpower, LLC
290 MWIn study Upton, TXERCOT Sep 2025target 2029
Onshore wind project J4006, Ringgold County
Onshore wind
290 MWIn study Ringgold, IAMISO May 2025target 2030
Onshore wind project J3902, Jefferson County
Onshore wind
289 MWIn study Jefferson, TXMISO Feb 2025target 2028
Baker Branch BESS
Battery storage · Mockingbird Storage Center, LLC
287 MWIn study Lamar, TXERCOT Jun 2025target 2029
Fivemile Wind
Onshore wind · Longview Wind, LLC
282 MWIn study Dawson, TXERCOT Apr 2025target 2028
Treehouse Solar
Solar + storage · Treehouse Solar, LLC
282 MWIn study Grimes, TXERCOT Jul 2025target 2028
Jukebox Solar
Solar · ACE DevCo NC, LLC
281 MWIn study Frio, TXERCOT Jun 2025target 2027
Battery storage project GEN-2024-170, Cass County
Battery storage
280 MWIn study Cass, MOSPP Mar 2025target 2028
Solar project AG2-453, Kendall County
Solar · Fox Valley Energy Facility, LLC
280 MWIn study Kendall, ILPJM Feb 2025target 2024
Sandcut Storage
Solar + storage · Hoosier Energy / Solvenz
280 MWIn study Vigo, INMISO Dec 2025target 2028
Pease River Solar
Solar · Pease River Solar LLC
276 MWIn study Foard, TXERCOT Dec 2025target 2029
Other project Q582, Maricopa County
Other
275 MWIn study Maricopa, AZWest May 2025target 2030
Other project PP00046, Richmond County
Other
275 MWIn study Richmond, NCSoutheast Aug 2025target 2029
Solar + storage project GEN-2024-166, Sedgwick County
Solar + storage
275 MWIn study Sedgwick, KSSPP Mar 2025target 2030
Solar + storage project T2-023, Juab County
Solar + storage
275 MWIn study Juab, UTWest Sep 2025target 2026
Onshore wind project J3846, Newton County
Onshore wind
275 MWIn study Newton, INMISO Jan 2025target 2030
Roboman Solar
Solar · Roboman Solar, LLC
273 MWIn study Coke, TXERCOT Jul 2025target 2029
Gas project AH1-734, Indiana County
Gas · Armstrong Power, LLC
270 MWIn study Indiana, PAPJM Apr 2025
Solar project J1890, Sabine Parish County
Solar
270 MWIn study Sabine Parish, LAMISO Apr 2025target 2027
Madison County Combustion Turbine
Gas · Indiana Municipal Power Agency (IMPA)
268 MWIn study Anderson, INMISO Aug 2025target 2028
Gas project E0034, Brookings County
Gas · Basin Electric Power Cooperative
265 MWIn study Brookings, SDMISO Aug 2025target 2027
Orient Energy Center
Gas · MidAmerican Energy Company
265 MWIn study Adair, IAMISO Aug 2025target 2027
Gas project FC100382, Osceola County
Gas · Duke Energy Florida, LLC
265 MWIn study Osceola, FLSoutheast Dec 2025target 2030
Gas project FC100386, Osceola County
Gas · Duke Energy Florida, LLC
265 MWIn study Osceola, FLSoutheast Dec 2025target 2030
Wind + storage project GEN-2024-278, Lea County
Wind + storage
264 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project Q2510, Maricopa County
Battery storage
264 MWIn study Maricopa, AZWest Feb 2025target 2028
Battery storage project GEN-2025-SR28, Beaver County
Battery storage
263 MWIn study Beaver, OKSPP Aug 2025target 2027
Surplus; J500
Gas
263 MWIn study Adair, IAMISO Jul 2025target 2027
Velociraptor BESS II
Solar + storage · Greyhound BESS 3 LLC
261 MWIn study Ector, TXERCOT May 2025target 2028
Velociraptor BESS I
Solar + storage · Greyhound BESS 2 LLC
261 MWIn study Ector, TXERCOT May 2025target 2028
Gas project 977773, Richmond County
Gas
260 MWIn study Richmond, NCSoutheast Jun 2025
Battery storage project PP00027, Wayne County
Battery storage
260 MWIn study Wayne, NCSoutheast Apr 2025target 2028
Jay Flat BESS
Battery storage · Jay Flat BESS LLC
259 MWIn study Kent, TXERCOT Jan 2025target 2029
Battery storage project E0017, Lincoln County
Battery storage · Union Electric Company d/b/a Ameren Missouri
258 MWIn study Lincoln, MOMISO Aug 2025target 2028
Horsepower BESS
Battery storage · Horsepower BESS, LLC
258 MWIn study Bexar, TXERCOT Dec 2025target 2028
Nuclear project AH1-710, Salem County
Nuclear · PSEG Nuclear LLC
257 MWIn study Salem, NJPJM Apr 2025
Solar + storage project ERAS-2025-018, Roosevelt County
Solar + storage
256 MWIn study Roosevelt, NMSPP Oct 2025target 2030
Solar project J3050, Calhoun County
Solar
255 MWIn study Calhoun, MIMISO Jul 2025target 2027
Onshore wind project J3971, Huron County
Onshore wind
255 MWIn study Huron, MIMISO Apr 2025target 2029
San Gabriel Solar
Solar + storage · San Gabriel Solar LLC
255 MWIn study Milam, TXERCOT Jan 2025target 2028
Clairemont Solar 1
Solar · Clairemont Solar LLC
252 MWAgreement signed Kent, TXERCOT Jan 2025target 2029
Velociraptor Solar II
Solar + storage · Greyhound Solar 3 LLC
252 MWIn study Ector, TXERCOT May 2025target 2028
Paint Brush PV2
Solar · Renew Development HoldCo LLC
252 MWIn study Coleman, TXERCOT Dec 2025target 2028
Paint Brush PV3
Solar · Renew Development HoldCo LLC
252 MWIn study Coleman, TXERCOT Dec 2025target 2029
Cowboy Power Gas Plant
Gas · Vaquero Power, LLC
252 MWIn study San Patricio, TXERCOT Aug 2025target 2028
Paint Brush PV4
Solar · Renew Development HoldCo LLC
252 MWIn study Coleman, TXERCOT Dec 2025target 2029
Paint Brush PV1
Solar · Renew Development HoldCo LLC
252 MWIn study Coleman, TXERCOT Dec 2025target 2028
Althea Storage
Battery storage · Sugaree Solar LLC
251 MWAgreement signed Maverick, TXERCOT Feb 2025target 2028
Oak Valley Solar
Solar · Oak Valley Solar LLC
251 MWIn study Navarro, TXERCOT Apr 2025target 2029
Page 11 of 37

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)