BATTERY STORAGE · MISO

Battery storage project E0017, Lincoln County

Battery storage project E0017, Lincoln County is a 258 MW battery storage request in interconnection study in the MISO interconnection queue, in Lincoln County, Missouri, connecting to Ameren Missouri.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
E0017
Grid region
MISO (Midcontinent)
Utility / transmission owner
Ameren Missouri
Developer
Union Electric Company d/b/a Ameren Missouri
Connection point (POI)
Harley-Pike 161kV
Location
Lincoln County, Missouri
Technology
Battery: 258 MW
Total requested
258 MW
Service type
Network resource (NRIS)
Study phase
Request Status: Active; Post GIA Status: Not started
Queue status
Active
Entered queue
6 August 2025
Proposed online date
August 2028

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem