United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTJay Flat BESS
Jay Flat BESS is a 259 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Kent County, Texas.
Queue statusIn planning
- PlanningQueued Jan 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0447
- Grid region
- ERCOT (Texas)
- Developer
- Jay Flat BESS LLC
- Connection point (POI)
- 59908 Novaprime 345kV
- Location
- Kent County, Texas
- Technology
- Battery: 259 MW
- Total requested
- 259 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 28 January 2025
- Proposed online date
- February 2029
Location
Marker shows the centre of Kent County; the queue data does not give exact sites.
Other requests in Kent County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem