United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTClairemont Solar 1
Clairemont Solar 1 is a 252 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Kent County, Texas.
Queue statusConsented
- PlanningQueued Jan 2025 (completed)
- ConsentedNov 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 27INR0435
- Grid region
- ERCOT (Texas)
- Developer
- Clairemont Solar LLC
- Connection point (POI)
- 59908 Novaprime 345kV
- Location
- Kent County, Texas
- Technology
- Solar: 252 MW
- Total requested
- 252 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 28 January 2025
- Agreement signed
- 24 November 2025
- Proposed online date
- February 2029
Location
Marker shows the centre of Kent County; the queue data does not give exact sites.
Other requests in Kent County