🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Althea Storage

Althea Storage is a 251 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Maverick County, Texas.

Queue statusConsented
  1. PlanningQueued Feb 2025 (completed)
  2. ConsentedSep 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
27INR0465
Grid region
ERCOT (Texas)
Developer
Sugaree Solar LLC
Connection point (POI)
Tap Escondido (8260) - Brackettville (8252)
Location
Maverick County, Texas
Technology
Battery: 251 MW
Total requested
251 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
12 February 2025
Agreement signed
29 September 2025
Proposed online date
September 2028

Location

Marker shows the centre of Maverick County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Maverick County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem