United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Senator Aggreko Solar

Senator Aggreko Solar is a 251 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Maverick County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2024 (current stage)
  2. ConsentedDec 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0311
Grid region
ERCOT (Texas)
Developer
Senator Aggreko Solar LLC
Connection point (POI)
138 kV Sunglow Substation (#78016)
Location
Maverick County, Texas
Technology
Solar: 251 MW · Battery
Total requested
251 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
2 February 2024
Agreement signed
31 December 2025
Proposed online date
October 2026

Location

Marker shows the centre of Maverick County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Maverick County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem