OTHER Β· ERCOTFort Duncan BESS
Fort Duncan BESS is a 106 MW other request suspended in the ERCOT interconnection queue, in Maverick County, Texas.
Queue statusPaused / redesign
- PlanningQueued Aug 2021 (current stage)
- ConsentedDec 2022 (not yet reached)
- Construction (not yet reached)
- OperatingJun 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 23INR0350
- Grid region
- ERCOT (Texas)
- Developer
- Fort Duncan BESS LLC
- Connection point (POI)
- 78015 Rosita Creek ROSICR 138kV_x000D_ will be at the new LCRA_x000D_ TSC Sunglow Substation
- Location
- Maverick County, Texas
- Technology
- Other: 106 MW
- Total requested
- 106 MW
- Study phase
- IA
- Queue status
- Suspended
- Entered queue
- 16 August 2021
- Agreement signed
- 12 December 2022
- Proposed online date
- June 2025
- Came online
- June 2025
Location
Marker shows the centre of Maverick County; the queue data does not give exact sites.
Other requests in Maverick County
- Sugaree SolarSolar Β· 251 MW Β· agreement signed
- Althea StorageBattery storage Β· 251 MW Β· agreement signed
- Escondido BESSBattery storage Β· 10.0 MW Β· agreement signed
- Senator Aggreko SolarSolar + storage Β· 251 MW Β· in study
- Old Victory Energy CenterBattery storage Β· 203 MW Β· in study
- De Los SantosBattery storage Β· 201 MW Β· in study
- Serrano StorageBattery storage Β· 186 MW Β· in study
- Senator Aggreko StorageSolar + storage Β· 153 MW Β· in study
- BRP Pueblo II BESSOther Β· 10.0 MW Β· built
- BRP Pueblo I BESSOther Β· 10.0 MW Β· built
- Trevino SolarSolar Β· 216 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem