United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in West (non-ISO utilities) — page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,857519.1 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,857 requests · page 11 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project C013, Meagher County
Onshore wind
326 MWIn study Meagher, MTWest Jan 2021target 2024
Solar + storage project 655, Bear Lake County
Solar + storage · Aurora Solar LLC
325 MWPaused / redesign Bear Lake, IDWest May 2022target 2026
Other project 771, Baker County
Other
325 MWIn study Baker, ORWest Apr 2025target 2029
Solar + storage project GI-2025-03, Kiowa County
Solar + storage
325 MWIn study Kiowa, COWest Apr 2025target 2031
Solar + storage project G0817, Yakima County
Solar + storage
325 MWIn study Yakima, WAWest Oct 2022target 2025
Solar + storage project GI-CS-2025-21, Pueblo County
Solar + storage
325 MWIn study Pueblo, COWest Sep 2025target 2030
Solar + storage project Q388, Pinal County
Solar + storage
323 MWIn study Pinal, AZWest Mar 2021target 2025
Solar + storage project C2-208, Harney County
Solar + storage
320 MWIn study Harney, ORWest May 2022target 2027
Solar + storage project C2-152, Lake County
Solar + storage
320 MWIn study Lake, ORWest May 2022target 2028
Other project 106, Pima County
Other
320 MWIn study Pima, AZWest Dec 2021target 2024
Solar + storage project C2-182, Lake County
Solar + storage
320 MWIn study Lake, ORWest May 2022target 2029
Battery storage project S0028, Converse County
Battery storage
320 MWIn study Converse, WYWest Feb 2024target 2026
Solar + storage project C2-187, Lake County
Solar + storage
320 MWIn study Lake, ORWest May 2022target 2029
Wind + storage project 300, Stillwater County
Wind + storage
315 MWIn study Stillwater, MTWest Jul 2016target 2020
Solar + storage project Q359, Pinal County
Solar + storage
315 MWIn study Pinal, AZWest Sep 2020target 2023
Onshore wind project G0585, Klickitat County
Onshore wind
313 MWIn study Klickitat, WAWest Mar 2018target 2021
Solar + storage project Q89, Pinal County
Solar + storage
313 MWIn study Pinal, AZWest Jan 2022target 2026
Wind + storage project 2024-G7, Yavapai County
Wind + storage
313 MWIn study Yavapai, AZWest Nov 2024target 2028
Solar + storage project TI-19-0227, La Plata County
Solar + storage
310 MWPaused / redesign La Plata, COWest Mar 2021target 2027
Onshore wind project Q370, Coconino County
Onshore wind
310 MWIn study Coconino, AZWest Mar 2021target 2024
Onshore wind project G0366, Morrow County
Onshore wind
302 MWIn study Morrow, ORWest May 2009target 2014
Onshore wind project 83, Meagher County
Onshore wind
300 MWAgreement signed Meagher, MTWest Mar 2019
Onshore wind project 71, Meagher County
Onshore wind
300 MWPaused / redesign Meagher, MTWest Mar 2019target 2029
Onshore wind project C007, Meagher County
Onshore wind
300 MWIn study Meagher, MTWest Mar 2019target 2022
Onshore wind project 362, Wheatland County
Onshore wind
300 MWPaused / redesign Wheatland, MTWest Apr 2019target 2022
Battery storage project Company 213, Clark County
Battery storage
300 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Onshore wind project 407, Rosebud County
Onshore wind
300 MWIn study Rosebud, MTWest Feb 2021target 2024
Solar + storage project Company MB, White Pine County
Solar + storage
300 MWAgreement signed White Pine, NVWest Sep 2021target 2028
Onshore wind project 763, Power County
Onshore wind
300 MWIn study Power, IDWest Mar 2025target 2030
LA300W
Onshore wind
300 MWPaused / redesign Luna, NMWest Mar 2022target 2028
WMA300SB
Solar + storage
300 MWIn study Sierra, NMWest May 2025target 2029
Other project 607, Sweetwater County
Other · NextEra Energy Resources Interconnection Holdings, LLC
300 MWPaused / redesign Sweetwater, WYWest Jun 2021target 2025
Solar + storage project C2-39, Iron County
Solar + storage
300 MWIn study Iron, UTWest Apr 2022target 2025
Solar + storage project 772, Elmore County
Solar + storage
300 MWIn study Elmore, IDWest Apr 2025target 2030
Gas project S0035, Washington County
Gas
300 MWIn study Washington, UTWest Apr 2025target 2027
Onshore wind project GI-2006-1i, Weld County
Onshore wind
300 MWAgreement signed Weld, COWest Jan 2006target 2007
Solar + storage project Company MT, White Pine County
Solar + storage
300 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Solar + storage project Company 225, Clark County
Solar + storage
300 MWPaused / redesign Clark, NVWest Sep 2022target 2030
Solar project G0866, Sherman County
Solar
300 MWIn study Sherman, ORWest Jun 2023target 2027
Other project Q348, Coconino County
Other
300 MWIn study Coconino, AZWest Sep 2020target 2024
Solar project GI-CS-2025-05, Weld County
Solar
300 MWIn study Weld, COWest Sep 2025target 2029
Battery storage project T2-075, San Juan County
Battery storage
300 MWIn study San Juan, UTWest Sep 2025target 2027
Solar + storage project 145, Cochise County
Solar + storage
300 MWIn study Cochise, AZWest Dec 2022target 2025
Onshore wind project 2024-G5, Mohave County
Onshore wind
300 MWIn study Mohave, AZWest Aug 2024target 2029
Other project 62, Pima County
Other
300 MWIn study Pima, AZWest Sep 2018target 2023
Solar + storage project Q465, Maricopa County
Solar + storage
300 MWIn study Maricopa, AZWest Mar 2022target 2025
Other project CLPT G17, Laramie County
Other · NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Laramie, WYWest Apr 2022target 2025
Onshore wind project GI-2016-4, Lincoln County
Onshore wind
300 MWAgreement signed Lincoln, COWest Feb 2016target 2018
Onshore wind project Q497, Navajo County
Onshore wind
300 MWIn study Navajo, AZWest Mar 2023target 2027
Solar + storage project 311, Yellowstone County
Solar + storage
300 MWIn study Yellowstone, MTWest Feb 2017target 2021
Page 11 of 38

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)