United States › Grid › Interconnection queues › Colorado

SOLAR + STORAGE · WEST

Solar + storage project TI-19-0227, La Plata County

Solar + storage project TI-19-0227, La Plata County is a 310 MW solar + storage request suspended in the West interconnection queue, in La Plata County, Colorado, connecting to Tri-State Generation and Transmission Association.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
TI-19-0227
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tri-State Generation and Transmission Association
Connection point (POI)
Hesperus 115kV Substation
Location
La Plata County, Colorado
Technology
Solar: 155 MW · Battery: 155 MW
Total requested
310 MW
Service type
Network resource (NRIS)
Study phase
Suspended LGIA
Queue status
Suspended
Entered queue
15 March 2021
Proposed online date
May 2027

Location

Marker shows the centre of La Plata County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem