🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown2,255782.1 GW in total
In planning1,590scoping or awaiting consent
Consented or building265closest to connecting
Built400connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

2,255 projects · page 26 of 46
ProjectCapacityStageConnection siteFrom
Ayr Energy Storage
Battery storage · Kxp Alpha I Limited
150 MWConsents Approved Ayr 275/33kV Substation
SP Transmission (south Scotland)
Oct 2028
Balrobert Farm BESS
Battery storage · Elgin Energy Es Co Limited
150 MWScoping Knocknagael 132kV Substation
SSEN Transmission (north Scotland)
Oct 2032
BESS North Farm
Battery storage · Rewe 5 Limited
150 MWScoping Chickerell 400kV Substation
National Grid (England & Wales)
Nov 2031
Bishops Dal Energy Park
Battery storage · Renewable Energy Systems Limited
150 MWScoping BISHOPS DAL ENERGY PARK 132kV SUBSTATION
SP Transmission (south Scotland)
Oct 2030
Bridge BESS
Battery storage · Apatura Battery Ltd
150 MWScoping Torness 400/132kV
SP Transmission (south Scotland)
Oct 2031
Carnedd Wen Wind Farm
Onshore wind · Carnedd Wen Wind Farm Limited
150 MWScoping Mid Wales West 132kV Substation
National Grid (England & Wales)
Oct 2030
Clifton Lane 150MW BSS
Battery storage · Renewables North West Ltd
150 MWScoping Frodsham 132kV
National Grid (England & Wales)
Oct 2037
Cnoc Buidhe Wind Farm
Wind + storage · Cnoc Buidhe Wind Energy Hub Limited
150 MWScoping Cnoc Buidhe 132kV/33kV Substation
SSEN Transmission (north Scotland)
Apr 2030
Copper Nose BESS
Battery storage · Copper Nose Energy Ltd
150 MWScoping Fawley 132kV Substation
National Grid (England & Wales)
Oct 2036
Coylton 275kV Greener Grid Park
Battery storage · Coylton Energy Limited
150 MWScoping Coylton 275kV substation
SP Transmission (south Scotland)
Apr 2026
Downiebrae BESS
Battery storage · Downiebrae BESS Ltd
150 MWScoping Dalmarnock Storage BESS 132kV Substation
SP Transmission (south Scotland)
Apr 2028
Drum of Clunas Wind and Solar Park
Onshore wind · Broadhaven Distribution Limited
150 MWScoping Drum Of Clunas Wind 275Kv Substation
SSEN Transmission (north Scotland)
Oct 2031
Ebstree Road BESS
Battery storage · Voltwise Power Holdings Limited
150 MWScoping Staffordshire Connection Node B 132kV Substation
National Grid (England & Wales)
Oct 2037
Epworth PV & BESS Station
Solar + storage · Ibv Kelfield Solar Ltd
150 MWScoping Trent Valley North Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2035
Maesnant Energy Park
Onshore wind · Maesnant Energy Park Limited
150 MWScoping Chirk GSP
National Grid (England & Wales)
Nov 2033
Fairgreen Energy Storage
Battery storage · Renewable Energy Systems Limited
150 MWScoping Rayleigh Main 132kV Substation
National Grid (England & Wales)
Oct 2034
Feckenham Greener Grid Park
Battery storage · Statkraft UK Ltd
150 MWScoping Feckenham 400kV Substation
National Grid (England & Wales)
Oct 2032
Galileo 07 Limited
Solar + storage · Galileo 07 Limited
150 MWScoping Galileo 07 Limited 132Kv Substation
SSEN Transmission (north Scotland)
Oct 2032
Glennifer Road BESS
Battery storage · Drax BESS Neilston Limited
150 MWConsents Approved Glennifer Road BESS 132kV substation
SP Transmission (south Scotland)
Jul 2028
Glentaggart 150MW BESS
Battery storage · Brockwell Energy Limited
150 MWScoping GLENTAGGART 150MW BESS 132kV SUBSTATION
SP Transmission (south Scotland)
Oct 2030
Halbeath
Solar + storage · Halbeath Solar Ltd
150 MWScoping Halbeath 132kV Substation
SP Transmission (south Scotland)
Jul 2029
Hazel Solar
Solar + storage · Hazel Solar Ltd
150 MWScoping Hawthorn Pit GSP
National Grid (England & Wales)
Oct 2035
Kedrum Solar Farm
Solar + storage · Rosside Energy Limited
150 MWAwaiting Consents Blackhillock 275kV Substation
SSEN Transmission (north Scotland)
May 2030
Keith Solar Farm
Solar + storage · Keith Solar Pv Limited
150 MWScoping Keith Solar Farm 275kV Substation
SSEN Transmission (north Scotland)
Oct 2028
Kenley House Solar Park
Solar · Boom Developments Ltd
150 MWScoping Creyke Beck GSP
National Grid (England & Wales)
Oct 2039
Killoch BESS
Battery storage · Renewable Energy Systems Limited
150 MWScoping Killoch BESS 132kV Substation
SP Transmission (south Scotland)
Sep 2030
Lightsource Threepwood
Battery storage · Lightsource Renewable UK Development Limited
150 MWScoping Gala North 400/132kV Substation
SP Transmission (south Scotland)
Oct 2030
Lightsource Mount Annan BESS
Battery storage · Lightsource Renewable UK Development Limited
150 MWScoping Chapelcross 132/33kV
SP Transmission (south Scotland)
Oct 2031
Manor Farm Solar Park
Solar + storage · Cse42 Limited
150 MWScoping Fawley GSP
National Grid (England & Wales)
Oct 2036
Nant Y Maen Wind Farm
Onshore wind · Edf Energy Renewables Limited
150 MWScoping Nant Y Maen 132KV Substation
National Grid (England & Wales)
May 2032
Neilston 132
Battery storage · Neilston Energy Limited
150 MWBuilt Neilston 132kV Substation
SP Transmission (south Scotland)
Oct 2025
Norrington Gate
Battery storage · Adv 004 Limited
150 MWConsents Approved Melksham B 132KV Substation
National Grid (England & Wales)
Sep 2037
Noventum Yaxley
Solar + storage · Noventum Power Solar 3 Limited
150 MWScoping North Anglia Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2034
Ormonde Offshore Wind Farm
Offshore wind · Ormonde Energy Limited
150 MWBuilt Ormonde 33/132kV Offshore Substation
Offshore transmission owner
Prestwold BESS
Battery storage · Greentech Projects Holding UK Limited
150 MWScoping Derbyshire Connection Node F 132KV
National Grid (England & Wales)
Oct 2037
Recell at Penrhos (BEGA)
Other · Recell Energy Bloom Developments Limited
150 MWConsents Approved Penrhos GSP
National Grid (England & Wales)
Oct 2025
Riccarton
Solar + storage · M2 Energy Storage Limited
150 MWScoping Currie 275/132kV
SP Transmission (south Scotland)
Apr 2029
Rigg House Pv Farm
Solar · Fvs Dean Moor Limited
150 MWScoping Harker GSP
National Grid (England & Wales)
Oct 2037
SSE Ferrybridge BESS
Battery storage · Sse Battery Salisbury Limited
150 MWBuilt Ferrybridge B 132kV Substation
National Grid (England & Wales)
SSE Fiddlers Ferry Battery Energy Storage
Battery storage · Littleton Pastures Solar Limited
150 MWConsents Approved Fiddlers Ferry 275kV Substation
National Grid (England & Wales)
Feb 2027
Sutton Courtenay
Battery storage · RWE Generation UK Plc
150 MWScoping Didcot 132kV Substation
National Grid (England & Wales)
Oct 2037
Torfichen Energy Park
Wind + storage · Torfichen Energy Limited
150 MWScoping Torfichen Energy Park 132kV Substation
SP Transmission (south Scotland)
Oct 2030
Water Orton
Battery storage · Voltwise Power Holdings Limited
150 MWScoping Warwickshire Connection Node F 132kV Substation
National Grid (England & Wales)
Oct 2037
Weaver Island 150MW BESS
Battery storage · Weaver Island BESS Ltd
150 MWScoping Elton (Merseyside 132kV Substation)
National Grid (England & Wales)
Oct 2037
West Grimsby Farm
Solar · Elgin Energy Es Co Limited
150 MWAwaiting Consents Grimsby West 132kV Substation
National Grid (England & Wales)
Oct 2035
Westerton Lane BESS
Battery storage · Apatura Project 22 Ltd
150 MWScoping Busby 275kV
SP Transmission (south Scotland)
Sep 2029
Whitson BESS
Battery storage · Field Devco Ltd
150 MWScoping Whitson 275kV Substation
National Grid (England & Wales)
Oct 2037
Wilton Lion BESS
Battery storage · Sembcorp (Wilton BESS) Limited
150 MWBuilt Greystones A 275kV Substation
National Grid (England & Wales)
Witney BESS
Battery storage · Voltwise Power Holdings Limited
150 MWScoping Cowley GSP
National Grid (England & Wales)
Nov 2038
Woodland Ridge
Wind + storage · Cubico UK Development Limited
150 MWScoping Hawick 132kV Substation
SP Transmission (south Scotland)
Jul 2034
Page 26 of 46

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.